PSM Demands Better Maintenance Planning

Follow some pointers to succeed at sites covered by the statute.

By Roger Corley, Life Cycle Engineering

1 of 2 < 1 | 2 View on one page

The term OSHA 29CFR, 1910.119 can provoke angst in maintenance planners at chemical plants and other industrial facilities. Maintenance planning is quite detailed in any such facility — but those sites subject to this process safety management (PSM) statute must contend with significantly increased complexity of planning. Following the spirit and letter of the statute are extremely important for two primary reasons: keeping plant personnel safe and avoiding potential government fines. Although on the surface these seem like separate issues, connections exist between personnel safety and potential fines.

While the PSM portion of the regulations of the U.S. Occupational Safety and Health Administration (OSHA) is far reaching, one part affects the maintenance planner more than the rest. That person has the important task of screening the incoming requested work for key words such as “change,” “modify,” “add” or “delete.” In addition, the planner must pay special attention to the repair or replacement of equipment to preclude a mistake that could cause a safety, environmental or equipment issue. This is crucial for ensuring the safety of technicians, protecting the environment, and avoiding collateral damage to equipment; miscues in these areas can cost a company dearly. Doing everything I can as a maintenance planner to give the technician all the tools necessary to complete a job safely is something I always will be most proud of in my career.

Very few facilities I have worked in and around as a work management subject matter expert fall under the OSHA PSM statute. Most of them don’t do a particularly great job of managing changes within their plants. At plants that must comply with this statute, OSHA is very clear in the requirements for management of change (MOC). It’s simple and complex at the same time. The simple part is that any change not made “in kind” requires initiation of a MOC process. The complex part is determining exactly what “in kind” means. For example, some may consider that replacing a 3-in. 300-psi ball valve used for level control with another 3-in. 300-psi ball valve qualifies as a replacement in kind. However, if the valves’ Cv (flow coefficient), control mechanism or other factors don’t match, that may not be so.

I was fortunate to work for a long time in a facility that took this statute very seriously; it produced chlorine, phosgene, acids and caustic. The plant required process engineers to examine even a set point alteration on a vessel level or process flow change to determine the upstream and downstream effects and any unintended consequences of those changes on the process.

Working in a chemical plant that produced lethal material caused a paradigm shift in my thinking, making me very risk averse. So now, no matter where I go, I view processes through my OSHA 1910.119 eyes. Every site, whether or not subject to the OSHA statute, can benefit from the lessons learned from working in that environment. The maintenance planner should ask the same questions. Verifying drawings are correct, ensuring equipment is replaced “in kind,” and confirming the computerized maintenance management system (CMMS) captures the correct history will make your workplace a bit safer every day.

Practical Ideas

So, you’re a planner in a PSM-covered facility. How does the statute affect what you must do? Let’s walk through a typical process for planning a maintenance job.

1. What jobs should you plan? The simple answer is that all maintenance jobs can benefit from some level of planning. Replacing a reactor vessel obviously requires a much more detailed job plan than, say, swapping a manual discharge valve on a pump. However, you must look at both these jobs through your PSM glasses to ensure that things like material of construction, specifications, size, etc., are considered before any work takes place. Even something as simple as replacing a light bulb deserves some rudimentary planning: you should verify a bulb of the right wattage and base size is specified and available, and arrange for a ladder or stool, if necessary.

2. Is it really necessary to visit every job prior to planning? It is well known as a best practice to go to every site of a planned job before putting together the job plan. Visiting the job site allows you, as a planner, to see for yourself what the job entails. Putting eyes on the job can answer many questions that can’t get answered otherwise. On one occasion, while coaching a planner at a refinery, I was working with him on a particular job of replacing catalyst in a reactor tower. It was a very complicated job. During the process, I told him we needed to climb to the top to verify the flange sizes and fastener sizes and types. He argued the equipment drawings contained all this information. I replied that experience shows drawings don’t always reflect field changes during construction. So, we climbed the 80 feet to the top. The flanges were exactly like the drawing — but the fasteners weren’t. A couple of Class-150 flanges somehow got heavy hex fasteners that didn’t agree with the drawing. If we hadn’t looked at the job, the craftspersons would have made the same climb with the wrong-sized tools, a waste of their time. Fortunately, we did the right thing and took the next steps for a situation like this: checking the specifications, allowing for the correct size fasteners, and ensuring the drawing is updated if needed. An engineering review may be necessary as well.

3. What “tools” does a planner need? I put tools in quotation marks because some facilities I visit have a collective bargaining agreement that precludes the planner or supervisor from turning wrenches (using tools). Such facilities sometimes require different arrangements to ensure compliance with the collective bargaining agreement. This might include assigning a tradesperson to accompany the planner in case removing a guard or inspection plate is necessary to properly plan the job. Regardless, a planner should have some very basic supplies for correctly creating a job plan.

1 of 2 < 1 | 2 View on one page
Show Comments
Hide Comments

Join the discussion

We welcome your thoughtful comments.
All comments will display your user name.

Want to participate in the discussion?

Register for free

Log in for complete access.

Comments

No one has commented on this page yet.

RSS feed for comments on this page | RSS feed for all comments