Case Study: Valve Monitoring Spurs Major Changes

Plant achieves cost savings and more-proactive maintenance.

By Justin Putnal, TPC Group

1 of 2 < 1 | 2 View on one page

TPC Group had been meeting industry standards, achieving production goals and safely maintaining day-to-day operation for decades. However, we wondered whether we were missing critical issues in our daily operations. The expectation for continuous improvement became increasingly important.

As a leader in providing highly specialized lines of chemical products to major chemical and petroleum-based companies worldwide, TPC Group strives to be a dependable supplier to our business partners. The online reliability of our Houston Operations site — which primarily produces butadiene, butene-1, fuel products, isobutylene derivatives and polyisobutylenes — is critical to serving our customers.

Stuck In A Rut

The conventional thinking at TPC Group was driven by industry standards and regulatory compliance, not technology. As far as valve maintenance and operation, the company treated unpredictable valve failure as a routine part of running a complex petrochemical process and the cost of doing business. We operated in a reactive manner — safely addressing valve failures as they occurred.

Anything short of a failure was considered a small problem that might never amount to any downtime, and often went unnoticed due to the lack of severity. The assumption was that we would find small problems during monthly field checks.

Explore how to apply due diligence to process safety practices. Register for a  free webinar on Due Diligence in Process Safety now.

There were two key issues with our conventional thinking about small problems in valve maintenance.

First, our assumption that intermittent field tests would discover small problems wasn’t always accurate. When a technician manually examines a valve for less than one minute, once a month, the person might miss an intermittent problem. On occasion, the timing of the technician’s rounds would correspond with the moment in which a valve wouldn’t meet optimum level of performance. Sometimes, however, irregularities would occur long before or long after the inspection.

Second was the assumption that anything short of a complete valve failure didn’t require the same degree of attention as a complete valve failure. While it’s true that many small problems faced in the field may never result in downtime, they still can have significant impact. For instance, a control valve that isn’t working correctly and tracking set point can create considerable consequences over time on the business — both from a safety and financial perspective.

While a loss of three barrels per hour doesn’t sound like much, when it continues for an extended period of time the loss adds up very quickly. When we were relying solely on a monthly five-point check on the control valve, we might never have caught such a problem, resulting in the organization missing out on significant production revenue.

Further complicating our maintenance process was the use of a one-size-fits-all configuration for new valves. This facilitated rapid deployment during valve installations. In many cases, the generic configuration worked fine. Unfortunately, it didn’t truly meet the unique needs of certain valves. Too much air pressure on some valves might create excessive load on the device and make lifting off the seat take too long. On the other hand, not enough air pressure could prevent completely lifting off the seat. To maximize plant performance, the company’s plan needed all valves to be configured properly.

TPC Group’s process control team knew things had to change and began initiating that change. The company didn’t have a formalized valve-monitoring plan in place. Instead, it had established preventive maintenance or mechanical integrity programs for only the most critical control valves — even those programs weren’t as thorough as they could have been. The team was well aware of the many benefits of a strong predictive maintenance plan and knew that a best practices plan could transform the organization.

Overcoming Outdated Thinking

For most organizations, the biggest hurdle for implementing a formal monitoring plan is the cost of procurement and installation. We already had jumped that hurdle. In August of 2014, TPC Group had purchased AMS Device Manager with the ValveLink Snap-On application. In addition, the company already had installed the monitors necessary to keep close tabs on the hundreds of control valves in the field.

Unfortunately, relatively few people knew about the software and hardware purchased, and the system had not been implemented effectively. After fully understanding the tools we had in place, the team needed little time to become proficient with the new system and initiate utilization in the process areas where the company had migrated to DeltaV and upgraded its instrumentation to HART devices.

Using case studies and success metrics around predictive maintenance, the process control team was able to make a case to management for approval of the man-hours needed to get the asset management system configured and effectively implemented. Knowing that this was the first step toward a complete transformation of how we manage assets at the plant, the team did just that.

1 of 2 < 1 | 2 View on one page
Show Comments
Hide Comments

Join the discussion

We welcome your thoughtful comments.
All comments will display your user name.

Want to participate in the discussion?

Register for free

Log in for complete access.

Comments

No one has commented on this page yet.

RSS feed for comments on this page | RSS feed for all comments