Home » Articles » Process Puzzler
Perspective: Process Puzzler
Don't Be Stumped by a Sump
Several steps can help handle gasoline-laden vent gas.
THIS MONTH'S PUZZLER
Our refinery has a project to fully enclose all API separators and other equipment to meet stringent EPA regulations. This includes a concrete sump, 15-ft long, 10-ft wide, and 7-ft 2-in. deep, built in 1944 and buried in earth. We reckon the slop oil in the sump consists of a mixture of 70 mol-% gasoline and 30 mol-% water. The 8,000-gal sump has two pumps, each eight feet below ground level, operating at 100 gpm each. A structural engineer, with some trepidation, set the pressure limit at 15 inches of water column (IWC) and the vacuum at 1.5 IWC. The normal vent exits the roof, which is 15 ft above the sump, and then must go to an activated carbon bed (ACB) located 60-ft away; the ACBs are on the ground. The bed has a pressure drop of 0.5 IWC at 100 scfm air (60°F). A flame arrestor normally is installed upstream of the ACB and likely would add a pressure drop of 35 IWC at 1,000 scfh air. The emergency vent goes direct to the roof. How can we design these vents?
REPLACE THE VENT WITH A FLARE
In my experience the ACB canisters are spent in less than a month. A combustor pilot (burner) would be more appropriate (Figure 1). You can still use the ABC as an alternate protection whenever you have to work on the combustor. An ejector can overcome the pressure of the flame arrestor. You pull the gas with the ejector using fuel gas at a certain pressure as the motive media. This should not affect the sump pressure; on the contrary it would be pulling toward vacuum.
Arbues Maymi, senior process engineer
CITGO Refining and Chemicals Co., Corpus Christi, Texas
GET RID OF THE FLAME ARRESTOR
This design presents three issues: 1) potentially a large fire-case flow; 2) very low pressure/vacuum design loads; and 3) high pressure drop in the normal vent discharge pipe. All of these issues are possible showstoppers.
Based on the mixture, the fire-case flow with gasoline would be 88,000 scfh air. However, that's with all vertical sides exposed to fire. API-2000 allows for insulation (via F). What would be better insulation than dirt? For eight inches of concrete, typical for this type of sump, I calculated an F of only 0.105.
Then, there is the sump itself. Its wetted area would be 650 ft2. However, only the top is exposed to a fire in the sump room. That area is only 150 ft2.
And the water has an impact. Using Peng-Robinson, I calculated a second molar cut with the following properties: heat of vaporization of 203.9 BTU/lb., saturation temperature of 132.4°F, and molecular weight of 66.6. With 100% gasoline it would be 168 BTU/lb. Interestingly, the latent heat is a flat line between 5% and 50% mole water. The net result is a reduction of the fire-case flow to only 12,800 scfh air. Vacuum always is a limiting factor with pressure relief.
I would size the flow for as little pressure drop as possible. The lowest set point available is 0.9 IWC — start there for vacuum. Try for 15 IWC with pressure. Calculate the vent pressure drop and keep it below the total pressure. The first obstacle is the flame arrestor.
Getting rid of the flame arrester is a priority. At 2,400-scfh air, I estimated about 200 IWC pressure drop through the arrester. API-2000, "Venting Atmospheric and Low-Pressure Storage Tanks," paragraph 4.4.1.2, gives succinct support: "A flame arrestor is not considered necessary for use in conjunction with a PV [pressure/vacuum] valve venting to the atmosphere because flame speeds are less than the vapor velocities across the seats of PV valves." Paragraph 5.2, API-2210, "Flame Arresters for Vents of Tanks Storing Petroleum Products," provides further support, noting the U.S. Bureau of Mines says the critical velocity is 10 ft/sec. With the flame arrester, no vent is possible.
Sizing the normal vent depends on the in-breathing (vacuum) and out-breathing (pressure) limits established by the process. The flow into the sump sets the in-breathing while out-breathing is based on the pump. Without additional data, use the right end of the (heat flow) curve for two pumps as the flow into the sump. Although assuming both pumps are operating is conservative, this approach usually is acceptable for out-breathing. With the limits set, you can specify the normal and emergency (fire) vents.
Given the conditions, it might be tempting to eliminate the emergency vent and go with the normal vent alone. This usually is not acceptable but it's worth checking into. Crane's method for divided flow won't work but iteration using the flow for the normal vent with the emergency vent set point is effective.
Using a vendor's package, I sized a 3-in. normal vent with 6-in. piping and a 3-in emergency vent. I found that a 6-in. single inlet pipe would feed both vents. I estimated a set point of 11 IWC for the emergency vent, 0.9 IWC for normal vacuum and 4 IWC for pressure. Sizing the emergency vent is tricky because the tank is rectangular and the vendor program calls for a height; use an equivalent diameter based on the top area and ignore the height.
Dirk Willard, senior engineer
Ambitech Engineering, Downers Grove, Ill.
MARCH'S PUZZLER
We use a vacuum knockout pot to push vapor produced from a batch polymerization reactor and a neutralization tank to a caustic scrubber (Figure 2). Caustic is recirculated over a chevron demister and through packing. The vacuum is only about 12 psia to avoid losses from the polymer reactor, which contains a solid catalyst. The process periodically suffers from pH upsets in the neutralization tank, corrosion in the vacuum pot, poor temperature control, loss of vacuum from seals, fouling of the vacuum pump rings, and fouling in the demister pad, which only survives a few weeks. We're tearing down this process every week to avoid trouble and the cost is killing us. There's a further complication — we periodically use the batch reactor and tank to make other products. Can you suggest any ways to improve reliability?
Send us your comments, suggestions or solutions for this question by February 13, 2012. We'll include as many of them as possible in the March 2012 issue and all on ChemicalProcessing.com. Send visuals — a sketch is fine. E-mail us at ProcessPuzzler@putman.net or mail to Process Puzzler, Chemical Processing, 555 W. Pierce Road, Suite 301, Itasca, IL 60143. Fax: (630) 467-1120. Please include your name, title, location and company affiliation in the response.
And, of course, if you have a process problem you'd like to pose to our readers, send it along and we'll be pleased to consider it for publication.
More From This Perspective
Don't Be Stumped by a Sump
01/12/2012
Several steps can help handle gasoline-laden vent gas.
Foil Coil Destruction
12/13/2011
A number of steps may pre-empt problems
Chillers Require Cold-Eyed Review
11/09/2011
Readers suggest ways to avoid temperatures swings and trips.
Neutralization Requires Basic Rethink
10/06/2011
Waste disposal system shouldn't be treated as an afterthought.
Silo Holds Mysteries
08/23/2011
Readers ponder why an old tank failed.
Make Models Match
08/09/2011
Readers explain how differences in pressure can arise.
Prevent Pump Problems
07/05/2011
Readers suggest possible root causes and ways to improve performance.
Process Puzzler: Spike Tank Spikes
05/31/2011
Readers suggest how to avoid column feed tank problems.
Heat Exchanger Puzzler: Make the Best of a Blunder
05/04/2011
Readers suggest ways to get an incorrect exchanger to do the job.
Foil Future Fires
04/05/2011
Readers point to possible causes of a blaze.
Choose Cleaning Solvent Wisely
03/17/2011
Readers raise a variety of issues to consider.
Process Puzzler: Look Beyond The Valve
01/14/2011
Other factors can contribute to persistent valve leaks.
Vanquish Vexing Venting
12/13/2010
Try process-control and equipment changes to eliminate hydrogen losses.
Process Puzzler: Root Out Rumbling
11/11/2010
Measurements can confirm the cause of the problem in the fiber-glass piping.
Process Puzzler: Deal with a Decanter that Can't
10/14/2010
Readers recommend ways to save a standing separator.
Don't Impair Level Measurements
09/21/2010
Several factors can prevent two sensors from giving matching readings.
Keep Catalyst From Overheating
08/25/2010
Readers react to a fouling problem in an exchanger.
Successfully Satisfy Catalyst Requirements
07/14/2010
Readers recommend ways to remove excess oxygen and water.
Process Puzzler: Make Solid Progress
06/16/2010
Readers suggest ways to improve crystallizer controls.
Is an Expansion Joint Good For the Long Stretch?
05/19/2010
Contributors suggest how to handle thermal and water issues.
Process Puzzler: Put Railcar Loading Back on Track
04/21/2010
Readers suggest how to stop serious safety snags.
Add Other Options to the Mix
03/16/2010
Readers suggest how to improve a blending operation.
Take the Pressure Off Loading
02/16/2010
Readers suggest how to avoid risks during upsets.
Process Puzzler: Keep Incineration Safe
01/25/2010
Readers suggest how to deal with a cyanide-containing fuel.
Process Puzzler: Combat Column Contamination
12/15/2009
Readers suggest how to tackle a troublesome tower.
Process Puzzler: Guard Against Gas
11/10/2009
Readers suggest the source of a safety stumper.
Process Puzzler: Tell the Bosses the Truth
10/15/2009
Management’s goal for a material balance likely isn’t feasible.
Process Puzzler: Fix a Fluid Flow Flaw
09/15/2009
Readers suggest solutions for dryer difficulties.
Process Puzzler: Master a Musty Mess
08/13/2009
Readers suggest how to deal with a contamination source.
Tame a Troublesome Thermowell
07/23/2009
Readers suggest solutions for a fluid-bed corrosion issue.
Process Puzzler: Avoid Another Fatal Accident
06/19/2009
Readers consider the causes of a deadly fire.
Process Puzzler: Eliminate Evaporator Effect
05/21/2009
Readers solve an evaporation pump problem.
Process Puzzler: Kayo a Cascade Control Complication
04/24/2009
Readers suggest how to properly regulate an exothermic reaction.
Clear Up a Compressor Conundrum
03/23/2009
Readers decipher a compressor surge.
Process Puzzler: Sidestep a Scale-up Scare
03/04/2009
Readers grapple with a reactor production change.
February Process Puzzler: Isolate Electrical Incidents
02/03/2009
Readers unravel a wiring riddle.
Process Puzzler: Soothe a Skittish Supervisor
12/16/2008
Readers weigh the wisdom of cladding exchanger tubes to answer last month's Process Puzzler.
Get out of the Soup
12/02/2008
Readers clarify a consistency complication.
Quell a Quality Control Confrontation
10/27/2008
Readers recommend improvements for a pH control process
October Process Puzzler: Foil a Future Fire
10/13/2008
Readers suggest ways to improve safety at a cylinder storage site. Also, December's Process Puzzler: Improving coagulant consistency.
September Process Puzzler: Fix a Fast Fouling Filter
09/05/2008
Readers suggest ways to improve operation and safety. Also included is November's Process Puzzler Question.
October's Puzzler: Change Layout and Operating Procedures to Reduce Risk
08/13/2008
September 2008 Process Puzzler: Kayo a Drum Problem
08/13/2008
Readers suggest ways to improve the performance of a pot
Process Puzzler Question: Lengthen media life and reduce operating costs in a pressure filter
06/16/2008
Our pressure filter suffers from excessive cake build-up. Although some caking is necessary for efficient filtering, it would be desirable to extend the running time. What do you suggest? Also, do you have any ideas on how we can lengthen media life or reduce operating costs?
Process Puzzler: Deal with dryer drizzle
06/16/2008
Readers suggest ways to solve a spray interference problem
August 2008: Designing a desulfurization process
06/01/2008
How would you improve this design?
November Process Puzzler: Deter dryer difficulties
10/30/2007
Readers suggest how to improve reliability and avoid danger, in this month's Process Puzzler.
October Process Puzzler: Keep a float from sinking operation
09/27/2007
Readers suggest how to achieve reliable level measurement, in this month's Process Puzzler.
September Process Puzzler: Will steam get a plant into hot water?
08/31/2007
Readers offer advice about switching a clean-in-place procedure.
August Process Puzzler: Remove operating problems not just an impurity
08/01/2007
Readers suggest how to keep sludge from clogging equipment in this month's Process Puzzler.
July Process Puzzler: Blow away conveying system problems
07/06/2007
Readers suggest how to improve the reliability of a crucial blower in this month's Process Puzzler.
June Process Puzzler: Forestall furnace foibles
05/16/2007
Readers suggest how to address a hard-running vaporizer in this month's Process Puzzler.
May Process Puzzler: Quick fix needed!
04/24/2007
Readers recommend solutions for a pump control problem in this month's Chemical Processing Process Puzzler.
April Process Puzzler: What do we tell maintenance?
03/29/2007
Readers identify problems with a relief system in April's Process Puzzler.
March Process Puzzler: Does removal approach offer a quicksilver lining?
03/01/2007
Readers consider ways to clean mercury from scrubber blowdown in this month's Process Puzzler.
February's Process Puzzler: Improve a grandfathered unloading station
01/30/2007
Readers suggest ways to improve a grandfathered unloading station in this month's Process Puzzler.
January Process Puzzler: Sticky valve
01/03/2007
Readers offer ideas for the cause of a sticky valve in Chemical Processing's monthly Process Puzzler feature.
December Process Puzzler: Debug a weigh feeder
11/29/2006
Readers offer ideas for improving reliability of a weigh feeder in Chemical Processing's monthly Process Puzzler feature.
November Process Puzzler: Consider options for automation
10/31/2006
Readers suggest ways to automate an HCl absorber in this month's Process Puzzler in Chemical Processing.
October Process Puzzler: Improve centrifuge separation capacity, quality
09/29/2006
Readers offer suggestions to improve centrifuge separation capacity and quality in Chemical Processing's monthly Process Puzzler feature.
September Process Puzzler: Uncovering cause of solid build-up
09/14/2006
Readers offer suggestions to improve reliability of a vibrating screen in Chemical Processing's monthly Process Puzzler feature.
August Process Puzzler: Avoiding a future accident
08/22/2006
Readers suggest possible causes for a mysterious mixer explosion in Chemical Processing's monthly Process Puzzler feature.
July Process Puzzler: Prevent the burn-out of a mixer
06/28/2006
Readers suggest quick solutions to a solid-liquid mixing problem in Chemical Processing's monthly Process Puzzler feature.
May Process Puzzler: Boost the reliability of a solvent supply pump
05/25/2006
Readers suggest solutions to cavitation in this month's Process Puzzler.
April 2006 Process Puzzler: Fixing a Fouled Flue Gas System
03/11/2006
Readers identify the cause of poor absorption in flue gas system in this month's process puzzler.
Making sense of temperature sensing
01/06/2006
Readers provide solutions to a thermowell problem in this month's Process Puzzler.
Condensate cripples compressor
01/05/2006
Readers offer tips on how to keep a standby compressor ready for service.
Know when the end is near
01/02/2006
Chemical Processing's readers offer tips about how to determine resin-reaction end point.
Don’t waste your boilers
01/02/2006
Chemical Processing's readers offer tips about how to properly isolate a waste heat boiler.
Track that spill
01/02/2006
Chemical Processing's readers offer tips about how to locate and identify a chemical spill.
Prevent heat-exchanger plugging
12/30/2005
Readers suggest how to keep a solvent recovery system running smoothly.
Cure column hiccups
12/29/2005
Process Puzzler: Choose a pump wisely
05/25/2005
Readers offer tips about how to choose the best pump for slurry service.
Process Manufacturing Puzzler: Stop solvent losses
04/01/2005
A reader is sufferring significant solvent losses during his batch process. Read about how his peers might solve his problem.
Process Puzzler: Keep cables in their place
02/21/2005
A Chemical Processing reader was looking for a solution to a cable hanger problem. At his plant, a 200-lb. cable bundle supported by cable hangers fell and injured one man. Read what advice our readers had for him and take a look at next months' question.
Process Puzzler: Serve up better column operation
12/21/2004
Readers tackle Chemical Processing's process puzzler question and offer tips about how to keep a stripper column from flooding.
Print page