Perspective: Plant InSites

Improve Your Plant's Prospects

Keep economics and the lifecycle stage of a facility in mind .


By Andrew Sloley, Contributing Editor

Politics is about what's desired. Science is about what's possible. Engineering is about what's profitable. Without profit, our employers don't need us. If a plant becomes unprofitable the simplest and safest step is to shut it down.

Plant modifications -- to improve safety, environmental performance or product quality, to adapt to changing feeds or demands, or to meet other aims -- can impact profitability. We must keep economics in mind at all times when altering a plant.

Profitable modifications often relate to where a plant is in its lifecycle and so go through a series of stages: experience, innovation, expansion and replacement.

Experience. We face many unknowns with a new plant. After all, most are unique creations. The number of plants of a given type rarely is numerous enough to allow "standard" designs. Even nominally "identical" plants often must contend with different local conditions (climate), market needs, staff capabilities and other factors. Experience reveals the limitations and benefits of a specific plant.

We usually can build upon accumulated experience to reduce costs and improve operation. But that requires that we truly understand the plant. We must pay attention to what works and what doesn't and carefully apply our knowledge of engineering fundamentals to grasp what the plant does and why.

At this stage we often can achieve benefits at relatively low cost by focusing on a group of factors:

• fat in original equipment and process design — safety factors frequently are added at multiple levels;
• operating experience in control and how closely units can run to control margins;
• capacity versus flexibility limits in equipment; and
• proven pinch points in the plant and how to get around them.
The strategy is to remove minor bottlenecks and take advantage of demonstrated capacity in systems that have an operating margin.

Innovation. Once we've used our experience and minor modifications to make fuller use of the inherent capabilities of the process and equipment, modifications become more challenging and expensive. To keep investment down we must look at different ways of doing things. We must investigate process modifications and design innovations — with the idea of achieving improvements while keeping plant infrastructure changes to a minimum.

At this stage we may gain benefits, e.g., from altering process configuration, switching catalysts and upgrading equipment.

Remember that multiple factors often can support investments. A prime example is energy efficiency projects. Historically, it's been nearly impossible to justify such projects based only on energy savings. However, greater energy recovery may allow for plant changes -- which, while typically requiring additional capital, may make overall payback more attractive -- and obviate investment in auxiliary systems such as for cooling water supply.

The long-term survival of a facility often hinges on the ability of personnel to keep a plant in the first two stages of its lifecycle. That demands experienced engineers because they can find new ways to innovate. Experienced engineers understand plant limits better and comprehend what changes will work and why. Finding and taking advantage of well hidden but profitable opportunities require both process and equipment knowledge. Institutional failure to build and guard this knowledge is a key factor in decline of operating facilities.

Expansion. Eventually we will have removed all the original fat and made the low-cost changes. At that point the right modification may involve "a bigger hammer" -- i.e., replacing equipment with larger versions or adding units in parallel.

At this stage expenses start to spiral up. Infrastructure costs become important. In many plants, piping and utility system changes can dominate the cost for adding or replacing equipment. The tab for the equipment itself becomes a minor factor.

Fundamental economic questions get asked. Investment costs per unit of production often exceed those for a new plant. However, the changes still may make sense because the base plant asset already has been paid for. In addition, maintenance requirements for existing equipment often can influence the decision. The extra costs for improvements may look a lot more attractive when installed units otherwise require repair or replacement.

In the expansion phase the facility's future becomes uncertain. Changes require high costs. Competition with newer facilities becomes ever more difficult.

Replacement. At the final stage the cost-to-capacity or cost-to-improvement ratio becomes so high that a new plant offers important strategic advantages. Building it in a different location may reduce transport costs. It may enable effective integration of new equipment, processes and control schemes for maximum benefit. It may provide maintenance, environmental and safety improvements as well as other significant benefits. The plant gets replaced.

So, the lifecycle starts all over again.


Andrew Sloley is a Chemical Processing Contributing Editor. You can e-mail him at ASloley@Putman.net.


More From This Perspective

Improve Your Plant's Prospects
03/04/2010
Keep economics and the lifecycle stage of a facility in mind .

Check What You're Ordering
02/04/2010
A mistake on a purchase order can buy trouble.

Take a Load Off Loading
01/11/2010
Some pipelines may benefit from more than "optimum" insulation.

Plant InSites: Come Up With a Solid Estimate
12/14/2009
Use geometry to figure out the amount of material in storage or equipment.

Assess the Gravity of the Situation
11/09/2009
Flow systems without pumps demand particular attention.

Plant InSites: Don’t Make Problems for Your Plant
10/22/2009
Local fabrication may seem attractive but can degrade performance.

Will You Really Realize Energy Savings?
09/10/2009
Heat integration may deliver complications instead of expected benefits.

Cut Pump Speed to Cut Problems
08/10/2009
Lower rpm can translate into higher reliability.

Cut Pump Speed to Cut Problems
08/06/2009
Lower rpm can translate into higher reliability.

View Data from a Different Perspective
07/23/2009
Re-plotting by flipping the parametric lines can provide important insights.

Utility Systems: Don't Rely on Pot Luck
06/16/2009
Paying attention to the condensate system can keep you out of hot water.

Nix Nozzle Nuisances
05/20/2009
Avoid flow problems by considering the impact of inlet losses.

Keep Bundle Blunders at Bay
03/16/2009
Combining air coolers can provide savings but also pose problems.

Take Control Down a Level
02/23/2009
Sometimes you can design out the need for instrumentation.

Troubleshooting: Take to the Field
01/30/2009
Troubleshooting demands getting into the plant to inspect units.

Steam Systems: Simple Solutions Can Prompt Complex Problems
12/23/2008
Steam systems are especially susceptible to developing difficulties

Stripper Bares All
11/21/2008
Analysis reveals how operating practices compounded design mistakes

Full Vacuum Rating Isn't an Empty Benefit
10/16/2008
It often can provide important but underappreciated advantages for vessels

Plant InSites: Look Beyond the Lore
10/10/2008
Don’t rely on recollections about how a unit had performed

Right Vacuum Control Choice Takes the Pressure Off
08/07/2008
Choosing the proper recycle stream for regulation is crucial

Use water to check vessel integrity
06/25/2008
Hydrostatic testing offers advantages but requires care

Understand the cold facts about subcooling
06/04/2008
Systems sometimes can surmount major layout errors

Plant InSites: Cast a cold eye on columns
05/23/2008
Subcooling can complicate and compromise tower performance

Don’t stack the deck against yourself
03/14/2008
Always consider future expansions before finalizing layouts

Keep parallel pumps in line
02/13/2008
Mind the curves when using different size pumps.

Carefully check vendor references
10/30/2007
Determine the differences between a cited installation and yours, Andrew Sloley, contributing editor, says in this month's Plant InSites column.

Do some heavy thinking about light loads
10/01/2007
Cutting steam demand can get you into hot water, advises Contributing Editor Andrew W. Sloley, contributing editor, in this month's Plant InSites column.

Correct those disturbing lapses
08/31/2007
Keeping liquid in a reflux drum still can prevent problems, says Andrew Sloley, in this month's Plant InSites column.

Don’t look at precondensers in a vacuum
08/20/2007
Consider the impact of the downstream vacuum ejector on precondenser performance, advises Andrew Sloley, in this month's Plant InSites column.

Properly protect centrifugal pumps
07/11/2007
Consider various factors when selecting how to guard against low flow, Andrew Sloley says in this month's Plant Insites column.

Teaming two solutions can be counterproductive
06/06/2007
Sometimes things just don’t add up as expected. Andrew Sloley discusses how sometimes two solutions aren't always better than one solution.

Keep others from making “classic” mistakes
04/24/2007
A heat exchanger problem provides a textbook example of design limitations, according to Contributing Editor Andrew Sloley.

Don’t let parallel pumps cross you up
03/28/2007
Small differences with parallel pumps can lead to big difficulties, according to Andrew Sloley in this month's Plant InSites column.

Make sure you’ve got a good flange match
03/06/2007
Standard large-diameter flanges don’t necessarily mate. Andrew Sloley provides insight in this month's Plant Insites column.

Take the pressure off pressure control
02/19/2007
Linkage of other variables can stymie hot vapor bypass schemes, according to Andrew Sloley's Plant InSites column.

Understand and ontrol Hot Vapor Bypass
01/08/2007
Contributing Editor Andrew Sloley says pressure control technique works well if implemented properly, in this month's Plant InSites column.

Make jacketing your strong suit
12/05/2006
Small details in jacketed-pipe configuration can have a big impact, according to Chemical Processing's Contributing Editor Andrew Sloley.

Column configuration can cripple performance
09/21/2006
The importance of having the inherent capability to meet operating requirements and enable proper instrumentation performance is stressed by Contributing Editor Andrew Sloley.

Heat integration steps can present control problems
09/13/2006
The more energy prices rise, the more heat integration saves. However, heat integration steps can present complex control problems. Slip-ups in putting control systems in place can make operations nearly impossible. That certainly was the case at one unit using heat recovery.

Spot problems with adsorbents
08/14/2006
The longer-than-expected life of an adsorbent points up the need to always assess the consequences of system additions. While sometimes this may involve detailed calculations, simply looking to the laws of physics can eliminate potential headaches.

Keep a steady eye on measurements
06/19/2006
While engineers often strive to keep processes running without too much variation, measurements that don’t change may be a cause for concern not celebration, as one refinery can attest.

Find the real cause of pump gas up
04/17/2006
Simply blaming high feed temperature for inadequate suction isn’t enough when diagnosing pump problems. Read this article to get a laundry list of causes for pump gas up.

Keep measurements on the level
04/17/2006
Changes in liquid densities can throw off readings. Plants commonly rely on differential pressure (DP) cells to measure level. Read this month's Plant InSites for advice on how to solve these level problems.

Can you trust your sight glasses?
02/17/2006
Sight glasses are invaluable for troubleshooting towers and checking instruments. Improper connections can take a toll on accuracy.

Is achieving design conditions realistic?
08/29/2005
Many factors can influence how equipment should be operated.

Process Engineering: Inspect with your mind, not just your eyes
03/11/2005
A thorough inspection of plant equipment following tiny installations can prevent a lot of future problems. Go beyond just checking for compliance with drawings when looking at hardware and physically look at the equipment itself.

Process Engineering: Poor compressor design puts pressure on pumps
01/18/2005
When a poor compressor design put too much pressure on the pumps, a new solution had to be constructed.  Sometimes the ideal solution is just an intricate compromise.

Save a bundle solving pressure-drop problems
11/04/2004
Pressure drop in compressor-suction and interstage coolers often creates problems. In some cases, just a few pounds of extra pressure drop make a revamp unworkable.

Give gaskets a squeeze
09/16/2004
Reevaluate gasket use when operating conditions or maintenance procedures change.

Sidestep side-draw control surprises
07/01/2004
The simplest approach to control side-draw distillation columns uses flow control on the side product. This solution, however, is not ideal for all side-draw control situations.

Preheater points out the value of cooling off
05/12/2004
Lack of attention to detail in conceptual design can hide many sins. Put the problem aside and then ponder it again. A fresh look may lead to an even better solution.

Tackle Tough Services for Centrifugal Pumps with Care
03/11/2004

Don't Let Heater Control Get You Steamed
03/03/2004

Solutions Centers

The Optimized Plant

The Optimized Plant

Sponsored by Honeywell

Honeywell can help sustain the life of your assets and maximize the operational performance of your plant or mill.

Solutions for the Chemicals Industry

Solutions for the Chemicals Industry

Sponsored by SAP

Measure your performance against your peers and discover which functional areas you can improve. Includes manufacturing, supply chain, R&D, regulatory compliance (ie REACH), and customer management.

Business Performance

Business Performance

Sponsored by Honeywell

Improve performance and increase profitability with integrated, comprehensive solutions that protect your people, process and assets, while reducing costs and improving productivity.

Marketplace (Sponsored)