Print page

Home » Articles » Making it Work

Perspective: Making it Work

Modeling Speeds Capacity Expansion

Simulation allows evaluation of more options more quickly.


By Prashant B. Kokitkar, Eli Lilly and Company, and Jonathan Kadane, Aspen Technology, Inc.

Eli Lilly was faced with the challenge of finding additional capacity at one of its manufacturing facilities to accommodate a new process. Through a partnership between its process modeling and manufacturing groups, the company identified combinations of process adjustments and cycle time reductions that could provide the required capacity with no additional capital spending.

The modeling environment and toolset maintained by Lilly’s process modeling group, part of its central engineering group, enabled the rapid development of an overall process model and evaluation of over 150 unique combinations of process alternatives, ranging from cycle time improvements to addition of capital equipment.

The results were delivered within the same modeling environment the manufacturing group already uses for emissions monitoring. This effort has demonstrated the superior capability of the modeling environment compared to the spreadsheet-based systems now employed for other tasks — and has renewed interest in using it more widely for process improvement and technology transfer.

THE CHALLENGE
The facility has a number of batch unit operations that several processes can share. Lilly wanted to use the equipment for a new process. The challenge was to reduce the campaign of an existing process for manufacturing an active pharmaceutical ingredient (API) from approximately 40 weeks to 26 weeks or less, allowing the new process adequate time on the equipment. The project also had a tight schedule because the new process was to be moved into the plant within a year. If the existing process couldn’t be modified in time, it would have to be relocated to larger equipment in another building on the site or even to another plant — both options requiring considerable time and expense.

Meanwhile, the manufacturing engineering team was pursuing several process improvements, including optimizing current unit operations, telescoping two process steps into one, and raising process yield.

The project team at the manufacturing site recognized the complexity of the effort and collaborated with the process modeling group to explore whether modeling tools could assist with choosing the optimal production options.

THE MODEL
A high-level simplified process model was developed to capture the overall cycle time and yield of the relevant process steps. This model didn’t include all materials specified in the recipe. For example, water was used in place of specific process constituents; this allowed for both rapid model construction and acceptable accuracy (because the model isn’t used to carry out an overall material balance). However, the model structure would easily incorporate materials and other particulars to conduct a future detailed analysis if so desired.

Individual operations such as vessel charges, heating/cooling, material transfers and separations weren’t modeled. Instead, higher-level “unit procedures” (e.g., extraction or crystallization) were. Each unit procedure typically consists of just one or two operations, allowing modeling of the overall cycle time and yield for that procedure. This approach enabled rapid model development and, by using the integrated production planning and scheduling capabilities, quicker simulations of campaigns.

In total, over 150 scenarios were evaluated while capturing the essential information about the process. Figure 1 illustrates an example of the simplified model and production schedule.

The large number of options under consideration involved a number of scenarios, including:

• Eliminating a purification step, combining two consecutive steps into a single step, or both. These options would change cycle times for cleaning or turnaround between steps, reducing overall campaign time.
• Adding a duplicate set of equipment. Certain items, such as the filter/dryer, are significantly more expensive; so scenarios were developed and evaluated both with and without high cost items.
• Incorporating additional process improvements being made by the local manufacturing engineering group. These changes had to be considered both with and without the other options mentioned above for cycle time reduction.

{sidebar3}

Initially, 96 scenarios with different combinations of options were developed. Their results led to identifying an additional 60 scenarios. All 156 were simulated by setting up a production plan similar to the one depicted in Figure 2. Such an evaluation would have been impractical with the spreadsheet-based analysis on which manufacturing customarily relies.

Based on the production plan, the modeling system produces a more detailed schedule (Figure 3). Note the schedule also shows the utilization of Tank 2, the main bottleneck for the cycle time.

Because the model was developed at a very high level, it was easily verified by manually reviewing the recipe and comparing the results with known bottlenecks such as Tank 2. To evaluate purchasing of equipment to address the bottleneck, duplicate units (e.g., a second Tank 2) could easily be added to the equipment pool and the simulations repeated. A single scenario took 15–20 minutes to set up, simulate and capture results. Thus, all 156 scenarios could be simulated, summarized and analyzed in a matter of days.

Verifying that simulations have been set up correctly is straightforward using the model output, for example, by observing the build-up and consumption of intermediate material based on the production plan setup.

IMPRESSIVE RESULTS
The modeling effort produced several combinations of available options that met the campaign time reduction goal. The simulations demonstrated that process changes, without any new capital spending, could reduce cycle times to achieve the goal of 26 weeks per campaign. It also was clear from the results that adding extra tanks alone wouldn’t suffice and wasn’t cost-effective. The chosen scenario involved a combination of several small changes such as increasing batch size by 5%, doing without an extra wash during filtration, and eliminating a purification step.

The simulations produced in the modeling environment allowed the team to evaluate a much wider and more comprehensive set of change combinations than would have been possible using spreadsheet-based tools. In addition, the project was executed much more quickly.

The plant made the changes in late 2010 and has achieved its goal of 26-week campaigns.

Another benefit of the project is that it has spurred the manufacturing team to consider the modeling environment for other purposes. Today, efforts are underway to use it for technology transfer and evaluation of further process improvements.


PRASHANT B. KOKITKAR is a consultant engineer for Eli Lilly and Company, Indianapolis, Ind. JONATHAN KADANE is director of industry marketing for Aspen Technology, Inc., Burlington, Mass. E-mail them at pbk@lilly.com and jonathan.kadane@aspentech.com.


More From This Perspective

Modeling Speeds Capacity Expansion
02/02/2012
Simulation allows evaluation of more options more quickly.

Chlorine Plant Benefits From PEM Fuel Cells
12/05/2011
Skid-mounted stacks convert hydrogen directly into electricity.

Ethanol Plant Boosts Operating Margin
10/27/2011
Model predictive control enables plantwide optimization.

Nonlinear Models Enhance Distillation
10/04/2011
Production-data-based approach leads to improved efficiency of rosin column.

Multi-Facility Approach Provides Clarity
08/13/2011
Linking automation KPIs to business value identifies priorities for action.

Case Study: Digital Positioner Aids Air Separation
07/25/2011
Tighter control enables significant boost in argon output.

Mixer Seal Gets Major Makeover
06/02/2011
Novel retrofit prevents leaks and offers other benefits.

Digital Valve Controller Provides Lasting Savings
05/18/2011
Linkage-less non-contact unit successfully copes with vibration.

Online Analytics Improves Batch Operations
03/29/2011
Field trial shows value for fault detection and quality prediction.

Clamp-on Flow Meter Gains Firm Hold
01/27/2011
Site finds ultrasonic device provides easy installation and accuracy.

Discrete Event Simulation Offers Real Value
01/03/2011
Pharmaceutical plants gain design, troubleshooting and other insights from models.

WirelessHART Successfully Handles Control
12/06/2010
Tests on stripper and absorber show results rival those with wired devices.

Refinery Pumps Up Energy Savings
10/06/2010
Switching to a steam-driven pump enhances condensate return system.

New Flow Meter Boosts Solvent Recovery and Much More
09/09/2010
Improved measurement accuracy delivers better control and savings.

Pump Problem Defies Standard Solutions
08/03/2010
Internal casing wear causes excessive vibration and noise.

Chlorine Plants Cut Venting and Fuel Costs
07/08/2010
Advanced control enables more effective use of hydrogen byproduct.

Safety And The Environment -- "Zero" Really Adds Up
06/08/2010
Project gets field issues detected and addressed far faster and more effectively.

Cooling Water Treatment Provides Sound Results
04/29/2010
Teaming ultrasonics with corrosion inhibitors offers environmental and economic benefits.

Inventory: Plant Takes Stock
04/09/2010
Initiative on storeroom inventory provides sizable savings and more.

Advanced Diagnostics Pay Off
03/08/2010
Impressive results earn "HART Plant of the Year" honor.

Particles From Piping Pose Pump Problems
02/08/2010
Magnetic separators remove black powder to improve performance.

Focus on Critical Assets Pays Off
01/14/2010
Program avoids costly downtime and enhances planned shutdowns.

Cellulosics Conversion Gets a Boost
01/05/2010
Control system enhances operation of demonstration plant.

Case Study: Instruments Tame Troublesome Slurry
10/16/2009
Two-step approach allows resin plant to more accurately dose additive.

Case Study: Online Monitoring Pays Off
09/16/2009
Wireless system succeeds in avoiding costs and increasing uptime.

Case Study: Novel Approach Enhances Control System Upgrade
08/31/2009
Measures to mock-up wiring and limit project scope as well as operational improvements provided significant benefits.

Polymer Plant Achieves Record Output
07/09/2009
Faster batch turnarounds and better repeatability spur impressive results.

Case Study: Migration Boosts Batch Operations
06/23/2009
New control system improves consistency and halves batch creation time.

Non-invasive Wireless Monitoring Provides Fast Payback
05/31/2009
Use on steam traps and research freezers leads to energy savings and improved uptime.

Equipment Maintenance: Thermal Imaging Changes the Picture
05/07/2009
Pharmaceutical plant benefits by taking a different look at equipment.

Wireless Proves its Worth
03/20/2009
Plant's early experience leads to high value applications.

Speedy Upgrade Transforms Production
03/03/2009
Replacement of legacy control system offers immediate and long-term benefits.

Take The Guesswork Out Of Utility Management
02/19/2009
Balancing the load cuts utility costs at Eastman Chemical.

Batch Control Gets Easier
02/04/2009
Loop tuning package doesn’t demand steady-state operation.

Condition Monitoring Pays Healthy Dividends
10/27/2008
Massive site benefits from earlier detection of problems and better diagnosis of their causes

Integrated System Improves Operations
10/09/2008
Combined process control and safety system cuts costs and boosts efficiency.

Integrated System Improves Operations
09/16/2008
Combined process control and safety system cuts costs and boosts efficiency

Upgraded Cooling System Halves Energy Costs
08/13/2008
New layout and speed control also provide other benefits

Polystyrene Plant Gains Extra Output and More
07/14/2008
Automation upgrade also extends asset life and boosts reliability

Steam projects provide fast payback
06/26/2008
Louisiana petrochemical complex significantly cuts energy consumption

Hot cutover boosts control system migration
05/02/2008
Keeping critical unit running provides significant economic and implementation benefits

Portable conveyor speeds paint production
10/30/2007
Unit ensures a consistent flow of soft acrylic powder without lumps or sticking, improving the production of thermoplastic paint.

Ethanol plant boosts output and saves energy
10/16/2007
Implementation of advanced process control for distillation and dehydration steps allowed a Wisconsin plant to meet competing goals.

Membrane Boasts Material Benefits
09/11/2007
As economical separation of contaminants from natural gas becomes increasingly important, simulation eases the design of innovative module to remove carbon dioxide. Membranes offer potential advantages over other methods.

Chill out about cooling costs
08/20/2007
Plastic towers can offer economic and operational advantages, and now come in modular designs suitable for bigger loads. Converting to a plastic cooling tower can yield substantial savings.

Two bulk conveyors prove better than one
07/11/2007
Engineers at EaglePicher Corp. in Quapak, Okla., faced some unique problems in manufacturing high-purity isotopic chemicals and wound up addressing them via a unique solution.

Flame Modeling Provides Matchless Results
04/13/2007
A computer simulation helps solve a refinery combustion problem. Finding ways to limit NOx from fired heaters, especially under stringent environmental regulations, has become a major concern for the petroleum refining industry. Complying with new stricter regulations, a Texas refinery upgraded the burners in one of its large cylindrical furnaces.

Sample pump eliminates emissions
03/20/2007
A compact system significantly improves analyzer accuracy. This innovative turnkey solution for analyzer emissions is a solid-state pump with an ultra-sensitive pressure regulator that mixes a compatible gas with the analyzer samples to achieve a constant vent header pressure — even during times of plant upset.

The intrinsically safe fieldbus has arrived
02/09/2007
Fieldbus has proven its merit in bringing projects online more efficiently, allowing better diagnostics, and control, and reducing maintenance costs and inventories. However, it has been limited in intrinsically safe services. At last, technology has come through once again with a solution. The capacity barrier of FISCO has now been significantly surpassed by a novel split architecture design that has already proven itself in the field.

pH sensor stands up to tough conditions
01/08/2007
Design provides improved reliability in a polymer-precursor batch reactor. Sensors must respond quickly and survive a harsh environment. Poor probe reliability can make the difference between a process that makes money and one that doesn’t.

Outsourcing innovation development
10/31/2006
A new development method may allow breaking away from the pack as companies continue to employ outsource facilities that offer flexibility and foster innovation.

Implementing an operations management system
09/29/2006
Things are changing at warp speed. Manufacturing companies are collecting large volumes of data from data systems but improvements are possible only if the data are analyzed and developed into useful business parameters.

Sasol plant benefits from reliability improvements
09/14/2006
Sasol Solvents reduced operating costs by more than $2 million dollars at it’s plants in Sasolburg, South Africa. The efforts earned the facility the 2005 HART Plant of the Year Award.

Low flow injection improves scale-up of catalysts
08/07/2006
Dow Chemical recently developed a reactive catalyst for use in one of its production facilities. Indications were that this new catalyst could save the company millions of euros once it reached full-scale production. The challenge was transferring the recipe using this new reactive catalyst from the laboratory to the pilot plant and, ultimately, to the production level.

BP tackles Texas City failings
04/12/2006
British Petroleum's tragic March 2005 explosion has been well-documented through the press. Read here to find out how that tragedy spurred the development of a new program addressing management issues at BP.

ASM Outperforms Traditional Interface
03/14/2006
Forty percent of operators at a world-scale North American ethylene plant site discovered that problems were solved 40% faster using new operator interface.

Oil refinery minimizes manual tank measurements
02/10/2006
The strategy was to enhance plant profitability, increase throughput capacity, upgrade product yields and improve on-stream reliability. Read here to find out what they accomplished.

Neville Chemical upgrades efficiency and safety
01/03/2006
A self-cleaning filter not only allowed one company to add efficiency and safety, it also boosted competitiveness.

Keep heat-transfer-system repairs uneventful
08/26/2005
A good plan is the key to avoiding risks in the maintenance of systems using high-temperature organic fluids.

Summit greases its gears to serve global marketplace
08/25/2005
A lubricant manufacturer increases order accuracy and speeds fulfillment by implementing enterprise resource planning software.

Software Drives OEM Toward Efficiency and Energy Savings
06/23/2005
ABB designed software for its ACS800 drive so Curtis-Toledo could improve the operation of its rotary-screw compressors. The customized software can control the system pressure, air delivery, oil temperature and duty cycle directly from the drive.

Process engineering: Wastewater treatment plant goes the distance
05/17/2005
A mobile reverse osmosis (RO) system from USFilter effectively treated water at an abandoned fertilizer plant. This allowed system effluent to be discharged into Tampa Bay without environmental impact.

AMS benefits chemical plant from start to finish
04/08/2005
DuPont engineers chose Intelligent Device Manager software from Emerson Process Management to help manage all the data available from their instrumentation.

Featured Sponsor