Perspectives: Making it Work

Innovative Design Tackles Tight Plant Footprint

Dual distillation column approach enables installation of new ethanol extraction technology

By Art Goldmann, EPIC Modular Process Systems

A facility in Illinois wanted to test the viability of a new ethanol extraction technology. However, this would require building a distillation column in a location virtually impossible to reach. Moreover, the unit would have to fit within a tight footprint and its installation would involve intricate rigging. Yet the facility couldn’t be altered to accommodate the new process system. The distillation unit was an add-in to a larger project, and the rest of the facility layout already had been completed. In addition, because of ongoing operations, constructing the system onsite wasn’t an option. To further complicate matters, the installation path involved multiple doorways with fixed dimensions, overhead piping and conduits, and several 90° turns.

“The pre-design site visit was critical. There was no way we could have developed the proper skid design or the detailed rigging plan without that visit. Those measurements were critical, and the path was very tight. The final resting place for the skid was in a very small space along the back wall of the plant. The client knew they needed the distillation system, but they had no idea how to get the system to the final destination,” says Ken Sipes, manager of EPIC’s Process and Mechanical Group. “We knew a modular solution was the answer, but actually getting the skid into the plant meant we couldn’t design the system as one big skid. We had to get creative.”

In response to this problem, the EPIC team devised a two-skids-in-one design. This involved engineering and manufacturing two self-contained units that, when fully installed, would work as one seamless unit (Figure 1). System scale-up with HYSYS software and 3D CAD design were developed around this idea, using lab-scale data and process-and-instrumentation drawings from the client. Finite element analysis performed by an independent source confirmed that each skid would bear the stress of navigating a complicated installation path.

DESIGN OF THE TWO SKIDS
Column diameter and height, piping locations and equipment placement were carefully chosen to fit within the two skids. The final design includes two distillation columns, each comprised of five spools. Both columns are rated for 15 psig at 250°F and feature reflux loops to achieve higher ethanol extraction rates. A vacuum pump lowers required energy inputs for distillation within both columns. Special attention was paid to the process flow, to determine equipment placement in the two separate sections.

The first column receives a three-component feed stream. Water and ethanol come off the top of the column while solvent remains as the bottoms product. To conserve energy, solvent leaving the bottom of the column goes through a heat-exchanger loop to preheat the incoming feed. The rejected solvent then is pumped to an off-skid holding tank. Meanwhile, water and ethanol enter the second column where ethanol is recovered as the overhead product. A condenser located on the second skid condenses the ethanol, which goes to an off-skid holding tank.

Piping design was critical. Minimizing overall piping requirements to control project costs was a general goal. The process piping requirements had to be balanced with the piping necessary to connect the process across the two skids. As few connections as possible were desired to reduce potential problems in the handoff between the two skids. The connections between skids were assembled and hydro-tested at EPIC’s fabrication facility before being disconnected temporarily for the journey to the installation site.

SUCCESS
The project was delivered on time and on budget due to the innovative modular design. Following a carefully developed rigging plan, the system was transported and installed successfully at the client site. The overall project timeline was shortened because the skids were built at EPIC’s fabrication facility (Figure 2) while the large plant-upgrade project continued at the client site.

Installation and startup only took a few days because the “plug-and-play” system was fully tested before shipment. Once onsite in the final operational location, process connections and inter-skid connections were mated together and the system was brought online. The distillation unit is performing as planned, providing 91% ethanol extraction.

The entire project took four and half months from the first inquiry by the client to startup at the facility. Engineering, design and drawings accounted for eight weeks; fabrication and assembly consumed eight weeks; testing at EPIC’s shop took one week; delivery and installation required one week; and an on-site EPIC automation engineer provided training for one week.



ART GOLDMANN, P.E., is a senior project manager and process engineer for EPIC Modular Process Systems, St. Louis, Mo. E-mail him at agoldmann@epicsysinc.com.

More from this perspective...

Title

Clamp-on Flow Meter Gains Firm Hold

Site finds ultrasonic device provides easy installation and accuracy.

01/27/2011

Condition Monitoring Pays Healthy Dividends

Massive site benefits from earlier detection of problems and better diagnosis of their causes

10/27/2008

Cooling Water Treatment Provides Sound Results

Teaming ultrasonics with corrosion inhibitors offers environmental and economic benefits.

04/29/2010

Cyber Security Threats: Watch Out for Watering Holes

Process engineer learns the right way to guard against vulnerability.

05/15/2014

Digital Valve Controller Provides Lasting Savings

Linkage-less non-contact unit successfully copes with vibration.

05/18/2011

Discrete Event Simulation Offers Real Value

Pharmaceutical plants gain design, troubleshooting and other insights from models.

01/03/2011

Dust: Hidden Hazard Lurks

Facility finds danger from accumulated dust and effectively addresses it

07/14/2014

Equipment Maintenance: Thermal Imaging Changes the Picture

Pharmaceutical plant benefits by taking a different look at equipment.

05/07/2009

Ethanol Plant Boosts Operating Margin

Model predictive control enables plantwide optimization.

10/27/2011

Ethanol plant boosts output and saves energy

Implementation of advanced process control for distillation and dehydration steps allowed a Wisconsin plant to meet competing goals.

10/16/2007

Flame Modeling Provides Matchless Results

A computer simulation helps solve a refinery combustion problem. Finding ways to limit NOx from fired heaters, especially under stringent environmental regulations, has become a major concern for the petroleum refining industry. Complying with new stricter regulations, a Texas refinery upgraded the burners in one of its large cylindrical furnaces.

04/13/2007

Focus on Critical Assets Pays Off

Program avoids costly downtime and enhances planned shutdowns.

01/14/2010

Hot cutover boosts control system migration

Keeping critical unit running provides significant economic and implementation benefits

05/02/2008

Hydrogen Plant Cuts Fuel Consumption

Switch to structured foil catalyst also promises to extend furnace tube life.

02/13/2013

Implementing an operations management system

Things are changing at warp speed. Manufacturing companies are collecting large volumes of data from data systems but improvements are possible only if the data are analyzed and developed into useful business parameters.

09/29/2006

Innovative Design Tackles Tight Plant Footprint

Dual distillation column approach enables installation of new ethanol extraction technology

08/26/2014

Integrated System Improves Operations

Combined process control and safety system cuts costs and boosts efficiency

09/16/2008

Integrated System Improves Operations

Combined process control and safety system cuts costs and boosts efficiency.

10/09/2008

Inventory: Plant Takes Stock

Initiative on storeroom inventory provides sizable savings and more.

04/09/2010

Keep heat-transfer-system repairs uneventful

A good plan is the key to avoiding risks in the maintenance of systems using high-temperature organic fluids.

08/26/2005