Watch Out for Cross-Contamination

Commissioning can pose risks unless you plan carefully.


By Dirk Willard, Contributing Editor

It was a close call. An off-hand remark at a morning meeting prompted me to inspect cross-connecting piping between two products. No pancake isolated the two product lines to the tank farm. We dodged a bullet; everyone knew it but no one considered it a near-miss. Exhaustion has a funny way of distorting perspective.

Cross-contamination, the unintentional mixing of two streams, can lead to consequences ranging from ruined product to an accident resulting in a fire or explosion.

Such inadvertent mixing has caused, totally or in part, more than a few major accidents. At a Union Carbide pesticide plant in Bhopal, India, on December 2, 1984, an error in cross-connection initiated the worst accident in the history of the chemical industry ("Bhopal Leaves a Lasting Legacy").

Let's consider some ways to avoid cross-contamination. Obviously, documentation is critical. The site where I spotted the problem relied on an incomplete and inaccurate process and instrumentation drawing (P&ID). We called it the Bateaux Tapestry. It stretched about 50 ft × 6 ft across a wall; most of the new process was added in pencil — just as a caveman would have done it 50,000 years ago if he'd been a process engineer. I found it best to personally walk down the piping, which unfortunately wasn't labeled. It took hours, sometimes days, to trace lines. Ideally, a site should constantly update its P&IDs; at a minimum, it should update them at least a few months before any large project.

Besides P&IDs, other useful documentation includes: 1) isometrics ("Don't Devalue Isometrics"); 2) tie-point lists; 3) piping line lists; 4) commissioning drawings such as ones showing connections for pressure and other tests; 5) marshalling panel terminal drawings; and 6) equipment drawings.

Nothing is more valuable than looking at the equipment in the field. Train your operators, contractors and even the construction foreman to follow a walk-down procedure. Yes, I know it's a bother but teach a course on it! Use marked-up P&IDs prepared in advance by the engineer responsible and then reviewed by safety, environmental and any other stakeholders. Do a quality control check. You don't want to try to tie into a line that was removed two years ago or install two block valves — on two different drawings. Walk down the line with the constructor to update the drawings before making tie-ins. Inspect piping before insulating or burying out of sight — take dimensional photos, if possible. Construction must meet the needs of installation (lugs), testing and purging (taps) as well as operations and maintenance. Always think of pipe, equipment and instruments as temporary. Ask yourself, "How will I remove it to make repairs?" And, "How can I isolate equipment from the process and from the environment to clean it?"

Once you've got a plan, it's time to evaluate how you will use new piping in the future and, particularly, how you will prevent cross-contamination. Isolation works best with pancakes and, for electronics, by pulling wires on both ends but taking care there's a low-resistance ground (fire risk). Hasp-locked cabinets and breakers usually are considered sufficient but you can't turn on what isn't wired.

Double-block-and-bleed (DBB) isolation, the second best choice, only works well if the bleed is open, an impracticality in most chemical plants. Spectacle blinds are a good choice for frequent isolation, if space allows and corrosion isn't a problem. Use bright tags for isolations. I've seen a flagged pancake left behind on a relief valve. Ensure tags are complete, dated and bear contact information and the reason for the isolation; keep a tag list. Don't forget to isolate purges and tubing lines — you don't want them contaminated or corroded.

Frequently, processes are built without considering commissioning: hydrotesting, leak-testing, cleaning, purging and conditioning. Whenever necessary, modify systems for ease of commissioning. Here's something else you might not have thought of: lab tests for cleaning contaminants. When developing commissioning procedures, you probably think about the compatibility, i.e., flammability and health risk. Have you considered the potential chemical reactions from cleaning and conditioning agents? Do you have lab tests for these species? Have you pondered what byproducts they might form with oils, lubricants and other compounds?

A small specialties plant I consulted for switched its packed distillation towers from fish oil to lubrication oil purification but didn't do any lab work in advance. It was surprised when slugs of brown gel fouled the packing and dripped off sample lines. In the end, we had to add filters everywhere. A simple lab experiment could have foretold what the chemistry had in store for us.

There's more to cross-contamination than meets the eye. It's always better to mull over the potential problems before a contamination incident than after when you're in a rush to startup.


DIRK WILLARD is a Chemical Processing Contributing Editor. You can e-mail him at dwillard@putman.net


More From This Perspective

Watch Out for Cross-Contamination
01/26/2012
Commissioning can pose risks unless you plan carefully.

Make Your Drawings Match Your Process
12/21/2011
Outdated P&IDs can lead to tragedy

Savor Construction Sites
11/17/2011
But make sure the excitement remains enjoyable.

Don't Devalue Isometrics
10/19/2011
They sometimes can tell you a lot more than P&IDs

Silence Kills
09/26/2011
Foster an atmosphere where workers speak up about concerns.

Work On Workarounds
08/31/2011
Treat them as problems that can compromise plant safety.

Succeed at Process Troubleshooting
08/08/2011
Take advantage of five easy techniques to find the root cause of problems.

Survey the Sources of Electrical Risks
06/14/2011
A walk-down helps determine the need for purged electrical boxes.

Don't Push the Envelope
05/05/2011
Take a sensible approach to avoid ignition dangers.

Don't Zone Out On Area Classifications
04/06/2011
Electrical ratings must start with analysis of chemicals present.

Know Your Rights
03/03/2011
Intellectual property agreements can pose significant concerns.

Heat Exchangers -- Keep Out of Hot Water
02/03/2011
Some simple steps can ease heat exchanger commissioning.

Stop Loops Driving You Round the Bend
01/12/2011
Practical pointers trump educators' edicts for real-world process control.

Do Your Level Best
11/29/2010
Level control with dP transmitters appears simple but really isn't.

Weak Oversight Can Doom a Project
11/02/2010
Don't timidly accept whatever a contractor proposes.

Keep Confined Space Work Safe
09/27/2010
Rigorous attention to detail is essential to minimize risks and enhance response.

Avoid Surprises During Pump Startup
08/26/2010
A well-thought-out approach can eliminate potential problems.

Size Pumps Like a Pro
07/01/2010
Use a step-by-step process to avoid pitfalls.

Use Ergonomics To Improve Safety
06/03/2010
During design always consider ease of construction and use.

Expand Your Plant Not Your Problems
05/10/2010
Careful project planning and good communications with vendors can avoid hassles.

Treat Rules of Thumb Right When Measuring
04/01/2010
These rules can save time but require a strong dose of skepticism.

Take the Write Steps for Career Advancement
03/03/2010
The ability to compose clear and effective documents is an important asset.

Avoid a Bad Turn
02/05/2010
Centrifugal pump selection demands attention to details.

Learn Office Politics
01/07/2010
Improving your political savvy can help you survive.

Safety Statistics Can Get You into a Scrape
12/03/2009
Focusing on minor accidents can foster false perceptions.

Properly Estimate Engineering Hours
11/06/2009
Don’t come up short on a project.

Don’t Gamble With LOTO
10/12/2009
Develop a common-sense plan for lockout/tagout.

Field Notes: Strive for a Surveyor’s Eye
09/02/2009
Surveying and drafting skills can pay off for process people.

Abandon-in-Place Must End
08/03/2009
Leaving equipment derelict instead of demolishing it can prove costly.

Please Don’t Hire Me!
07/06/2009
Some contracts simply aren’t worth winning.

Take the Right Approach to Projects
06/12/2009
Remember the real fun begins after approval.

Don't Dismiss Process Flow Diagrams
05/14/2009
Understand the role these diagrams can play and how to use them effectively.

Don't Let Design Errors Doom Your Project
04/16/2009
Engineering quality assurance demands more attention than it usually gets.

Reduce Your Energy Needs
03/10/2009
Achieving savings may provide a powerful career boost.

Brain Drain Brings Big Headaches
02/15/2009
Inexperience and a tough production schedule can be a lethal combination

Choose Your Next Position Wisely
01/20/2009
Finding your dream job takes a bit of soul searching and answering some tough questions.

Finding The True Cost of Data-Collecting Equipment -- Can You Really Afford It?
12/15/2008
Consider all costs before you opt to install an instrument.

Deftly Deal with Management of Change
11/20/2008
Consider some proven tactics to survive this grueling process.

Make the Most of Contractors
10/15/2008
Using hired help effectively starts by treating them as part of your team.

Correctly Manage Change
10/10/2008
How you begin is at least as important as your eventual goal

Solve the real problem
08/27/2008
Sometimes solving a problem causes more harm than good

Get Pipe Specifications Right in the Beginning!
08/08/2008
Good pipe specifications can avoid costly and dangerous mistakes

Keeping Peace While Managing Unions
08/07/2008
Dealing with unions often poses challenges to engineers

Maintain an open mind about maintenance options
06/17/2008
Sometimes it’s better to take a preventive rather than predictive approach

A haphazard approach can hobble hazard reviews
06/02/2008
Taking some simple steps can help you avoid common pitfalls in assessing changes

An Alert Operator Is a Safe Operator
04/24/2008
Maintaining a good work environment can contribute to a safer plant

Take a studied approach to plant studies
03/13/2008
Carefully address the challenges of managing and directing specialized teams

Stick to the basics
02/13/2008
Getting immersed in details can doom a basic design contract to financial failure.

It really isn’t your problem
02/05/2008
A manager shouldn’t try to be a Mr. Fix-it.

Build reliability in during design
12/19/2007
Instrumentation that promises to improve reliability may not always be what they seem. You have to consider whether a site can properly maintain sophisticated instruments.

Make the most of newly hired, experienced engineers
10/29/2007
Contributing Editor Dirk Willard reminds readers that an old dogs can learn new tricks and plants should keep this in mind when hiring new, yet experienced, engineers.

Learning foreign languages can make your job easier
10/04/2007
Don’t build walls, by ignoring foreign languages, says Contributing Editor Dirk Willard, in this month's Field Notes column. Learning foreign languages can make your job easier.

Don’t get zapped by spark testing
08/28/2007
Understand the intricacies of checking for defects in a liner, advises Dirk Willard, contributing editor, in this month's Field Notes column.

Electives can contribute significantly to professional growth
07/24/2007
Taking electives can help you broaden your skills, says Dirk Willard, in this month's Field Notes installment.

Protect your electronics
06/06/2007
Ignoring exposed electrical boxes can cost you a bundle, says Contributer Dirk Willard, in this month's Field Notes column.

Strike the Right Balance
04/30/2007
Make the walk-through your first line of defense, advises Dirk Willard in this month's Field Notes column.

Choose the right fluid for your pressure test
04/12/2007
Compressed gas often makes the most sense for checking a process, according to Senior Editor Dirk Willard, in this month's Field Notes column.

Pressure tests can spur successful start-up
03/01/2007
Push it: if it breaks it probably needed to be replaced, says Dirk Williard, in this month's Field Notes column. Doing so can help improve your processes.

Rely on an Ombudsman for a Smoother Project
02/12/2007
Working with someone who speaks the operator’s language will avoid problems, according to Dirk Willard, in this month's Field Notes column.

Know when to leave a sinking ship
01/03/2007
The unspoken truth about projects is that they all come to an end, according to Dirk Willard in this month's Field Notes column. The key, he says, is knowing when to leave.

Making Your Process Operator-Proof
12/05/2006
Senior Editor Dirk Willard discusses Shigeo Shingo's take on mistake-proofing, or Poke Yoke, if you speak Japanese. The practice suggests the following devices: eliminate — redesign, facilitate — guide, mitigate — lessen the damage caused by the error, or flag — identify the error.

Work to build coalitions with difficult teams
10/24/2006
Managing feuds is the first step toward a successful project, according to Senior Editor Dirk Willard in his monthly installment of Chemical Processing's Field Notes column.

Choosing the right contract
09/20/2006
A contract can be a stone in your shoe. Knowing which type of contract to choose can make your job easier. Chemical Processing's Senior Editor Dirk Willard provides tips on various types of contracts.

Remember the old reliable orifice plate
09/11/2006
The cost-effective dP flow meter is ideal for utility surveys, Senior Editor Dirk Willard says in this month's Chemical Processing Field Notes column.

Twisting the dragon's tail
08/18/2006
Complacency is a problem when violating safety rules has no repercussions.

Don’t Be the Hub of a Wheel
08/17/2006
Successful ‘green-field’ site start-ups depend on developing a team, says Senior Editor Dirk Willard.

Level transmitter — art not science
06/13/2006
There is much more to setting up a transmitter than a mere equation. Design and control errors can certainly compromise performance. Follow these simple tricks to get it right.

Solve the real problem
05/06/2006
Sometimes solving a problem causes more harm than good.

Field Notes: Don't Know Much Geometry
04/12/2006
The cornerstones of chemical engineering are often overlooked. Teaching theory to operators is crucial to safe operations, says Dirk Williard in his monthly Field Notes column.

Check out before you start up
02/28/2006
In his monthly Field Notes column, Senior Editor Dirk Willard reveals that regardless of the preparation, check-out tests always bring out some surprises.

A methodical approach to construction and commissioning
02/10/2006
A start-up is only as easy as the preceding steps: construction and commissioning, says Senior Editor Dirk Willard in his monthly column.

Don’t let a start-up finish you off
01/24/2006
Senior Editor Dirk Willard spent years as a "start-up" engineer. He advises that proper planning is crucial for achieving a happy ending.

Featured Sponsor