Diagram Process Design History: Don't Trip Up on Line Lists
Resolve discrepancies and other problems early.
"The test pressure seems too high." It was an honest criticism. We had based our line list on the design pressure of the vessel connected to the drain line and come up with 450 psi, with a testing pressure of 680 psi. However, previous hydrostatic tests of the nearby piping connected to that drain line only had been at 400 psi. Such are the challenges of developing a good line list. So, let's review what to consider when putting together a line list and some of the pitfalls.
The line list should define operating, average and maximum temperature and pressure, design temperature and pressure, pipe specification, special requirements (such as post-weld treatment for caustic and sulfur exposure), and hydrostatic test pressure. Most importantly, it must justify the values selected. A history is useful; to document design history, I make comments in a spreadsheet so they can be viewed later.
The line list should consist of two sections: mechanical and process. The mechanical section often only contains line numbers, connections and tie-points but sometimes includes the pipe specification; if the line list requires mating a 300-psi flange to a 150-psi one, it's mechanical's fault. The process portion covers corrosion, safety and pressure relief.
To develop the line list, you'll need: 1) an approved marked-up piping and instrumentation diagram (I never begin a line list without one!); 2) isometric drawings of normally open connecting pipe; 3) pressure safety valve (PSV) set pressures as well as design pressures for equipment and vessels — these may not agree; 4) field or distributed-control-system readings of average and maximum operating temperature and pressure, preferably over at least two to three years; 5) a process flow diagram (PFD) to define the stream composition and risk should a leak occur; 6) equipment curves, e.g., for pumps; 7) a unit operating manual — this is useful for understanding the unit operation, if the PFD isn't current, which is often the case; and, ideally, 8) a discussion with operations to confirm operating conditions — these frequently get lost in translation between project engineering and operation. If pressure readings are too remote, you may need a hydraulic analysis to estimate the true pressure in a pipe.
List the discrepancies among the collected data. A vessel design pressure may exceed the PSV set pressure. A pipe connected to one on the line list may not match the pressure desirable — usually, the highest pressure is chosen for the design pressure unless it conflicts with normally open connecting pipe. This is an important concept: base line list values on normal conditions, not worst case ones.
Design pressure usually is the vessel design pressure (especially if the pipe connects directly), the deadhead pressure of a pump or compressor, or the PSV set pressure. No hard and fast rules exist. If nothing else is available, refer to the plant standards or add, say, 50 psi to the maximum operating pressure.
Because the design temperature really represents fire conditions where metal softens and withstands less pressure, choose it with care. Normally, opt for the isometric temperatures, not the vessel design temperature. If possible, use the maximum operating temperature plus a safety factor of, say, 50°F. Tracing poses an additional problem. For steam tracing, select the normal saturation temperature of the steam supply. For electric tracing, I have seen 250°F used; constant wattage tracing can have an exposure temperature of 500°F.
Now, let's consider the pressure test. Hydrostatic testing is commonly chosen due to familiarity; some companies set a limit of 100 psig on pneumatic testing for "safety reasons," because of a lack of understanding of dynamics. (See: "Choose the Right Fluid for Your Pressure Test.")
It's good practice to test all utility pipes connected to the process at process pressures. Conduct the test at whichever is higher — the flange rating or the design pressure corrected for temperature — plus a 50% margin. For a design pressure of 300 psig, test pressure = 1.5×Ct×300, where Ct is the temperature correction factor for the pipe material. Here's a useful equation for the design-based test with carbon steel: test pressure = 1.5×(5.293×10-11×T4 – 8.710×10-8×T3 + 4.797×10-5×T2 – 8.656×10-3×T + 1)×design pressure, where T is in °F. The pressure mustn't exceed the flange limit set by the metallurgist — if this is a problem, change the pipe specification and probably the tie-point.
Lastly, most line lists require an inspection specification. For carbon steel, checking 10% of the welds is adequate; X-ray 100% of alloy welds.
DIRK WILLARD is a Chemical Processing Contributing Editor. You can e-mail him at dwillard@putman.net
More from this perspective...
| Title | Date |
|---|---|
|
A haphazard approach can hobble hazard reviews Taking some simple steps can help you avoid common pitfalls in assessing changes |
06/02/2008 |
|
Keep plant layout from laying you low Spot mistakes before they literally become set in stone on the site |
05/02/2008 |
|
An Alert Operator Is a Safe Operator Maintaining a good work environment can contribute to a safer plant |
04/24/2008 |
|
Take a studied approach to plant studies Carefully address the challenges of managing and directing specialized teams |
03/13/2008 |
|
Getting immersed in details can doom a basic design contract to financial failure. |
02/13/2008 |
|
A manager shouldnt try to be a Mr. Fix-it. |
02/05/2008 |
|
Build reliability in during design Instrumentation that promises to improve reliability may not always be what they seem. You have to consider whether a site can properly maintain sophisticated instruments. |
12/19/2007 |
|
Make the most of newly hired, experienced engineers Contributing Editor Dirk Willard reminds readers that an old dogs can learn new tricks and plants should keep this in mind when hiring new, yet experienced, engineers. |
10/29/2007 |
|
Learning foreign languages can make your job easier Dont build walls, by ignoring foreign languages, says Contributing Editor Dirk Willard, in this month's Field Notes column. Learning foreign languages can make your job easier. |
10/04/2007 |
|
Dont get zapped by spark testing Understand the intricacies of checking for defects in a liner, advises Dirk Willard, contributing editor, in this month's Field Notes column. |
08/28/2007 |
|
Sometimes a construction manager is a necessary evil, says Dirk Williard, in this month's Field Notes column. |
08/20/2007 |
|
Electives can contribute significantly to professional growth Taking electives can help you broaden your skills, says Dirk Willard, in this month's Field Notes installment. |
07/24/2007 |
|
Ignoring exposed electrical boxes can cost you a bundle, says Contributer Dirk Willard, in this month's Field Notes column. |
06/06/2007 |
|
Make the walk-through your first line of defense, advises Dirk Willard in this month's Field Notes column. |
04/30/2007 |
|
Choose the right fluid for your pressure test Compressed gas often makes the most sense for checking a process, according to Senior Editor Dirk Willard, in this month's Field Notes column. |
04/12/2007 |
|
Pressure tests can spur successful start-up Push it: if it breaks it probably needed to be replaced, says Dirk Williard, in this month's Field Notes column. Doing so can help improve your processes. |
03/01/2007 |
|
Rely on an Ombudsman for a Smoother Project Working with someone who speaks the operators language will avoid problems, according to Dirk Willard, in this month's Field Notes column. |
02/12/2007 |
|
Know when to leave a sinking ship The unspoken truth about projects is that they all come to an end, according to Dirk Willard in this month's Field Notes column. The key, he says, is knowing when to leave. |
01/03/2007 |
|
Making Your Process Operator-Proof Senior Editor Dirk Willard discusses Shigeo Shingo's take on mistake-proofing, or Poke Yoke, if you speak Japanese. The practice suggests the following devices: eliminate redesign, facilitate guide, mitigate lessen the damage caused by the error, or flag identify the error. |
12/05/2006 |
|
Work to build coalitions with difficult teams Managing feuds is the first step toward a successful project, according to Senior Editor Dirk Willard in his monthly installment of Chemical Processing's Field Notes column. |
10/24/2006 |