Perspectives: Field Notes

A haphazard approach can hobble hazard reviews

Taking some simple steps can help you avoid common pitfalls in assessing changes

By Dirk Willard, contributing editor

The room grew tense as the reliability engineer complained that the condenser being discussed was slated to be replaced during the next turnaround. The simulator model, the basis of the whole project, didn’t include this change. What had been a plant hazard analysis (PHA) quickly degenerated into a process review.

This is an excellent example of what can go wrong during such evaluations. So, let’s look at what you can do to make your PHA or hazard and operability (HAZOP) study go smoothly.

First, carefully consider the basis for the process change — the reason for the review. What’s the purpose? What’re the options? Of course, the particular situation may limit the choices. Is there a way to avoid safety problems, simplify a process, or reduce hazards? For instance, Can you improve mixing in a reactor and make it smaller? Or Can you eliminate recirculation lines (reducing hazardous inventories)? Which option offers the lowest total cost? Is this the safest option? Consider summarizing the choices in a table. The design team should present these thoughts in a report with a buy-in from the project leader before scheduling a PHA or HAZOP.

With the solution in hand, next account for the plant’s preferences — e.g., for a particular type of flow meter or for RTDs instead of thermocouples. Don’t completely rely on company standards. After all, one unit at the site may prefer steam tracing while another may only accept electric tracing. If these choices pose new safety issues, they need to be considered before the safety review.

Another often missed hazard is scheduling. Can your process change be implemented all at once or will several plant outages be required? Can the plant operate safely with the interim changes? How will other changes in parallel projects affect yours?

Then, of course, there’s operator training — you’ll want to avoid gaps in training. You also should assess how a change will affect operator workload.

Now, you’re ready for the process and instrumentation drawings (P&IDs). First confirm the battery limits and make sure the P&ID you start with is the latest revision. Don’t crowd your P&IDs; leave plenty of room for notes and equipment. When more detail is needed, notes can refer to other documents. Make sure old bubbles are removed. Use color, if possible, to highlight the changes. Don’t be afraid to add a second or third sheet to your drawing set.

Finally, prepare your presentation. Utilize all team members effectively. Don’t assume everyone is familiar with your process or project. Here’s what each attendee will need: 1) P&IDs; 2) process flow diagrams; 3) a material balance; 4) mechanical information; 5) the alarm/trip schedule; 6) the process description; and 7) the purpose of the review and the process changes.

Have reference material on-hand for consideration by your team. For instance, provide a drawing of the entire facility with the area affected by the hazard review highlighted. If equipment will change, create a table comparing the old and the new items. Make available summaries of past PHAs and HAZOPs of the area and accidents with excerpts of concerns listed for discussion during the review if necessary. Time-line via tables the maintenance history of relevant equipment.

Now you’re ready to do your review — but guard against common mistakes.

Hazard reviews often focus too much on operations without considering maintenance. When a new threat appears on the horizon, operation engineers prefer to slap in another instrument rather than use the ones they have in a new way. This adds to the maintenance workload.

Another problem is what I call “the boogie man effect.” Hazard reviews tend to produce unrealistic solutions and imaginary fears. In one case, a caustic scrubber was proposed for a remote unloading facility. Maintaining the scrubber at the proper concentration proved difficult. It sat idle, unfilled, and became a haven for spiders.

Another pitfall is equipment pressure limits. Use the ASME-defined temperatures not the limits for alarms and trips. The code fixes maximum allowable working pressure (MAWP); trips prescribe maximum allowable operating pressure (MAOP). Trip settings change; avoid ones above 80% of relief settings because that’s the point when valves start to open.

Once the meeting gets started the facilitator needs to get everyone involved. One idea is to go around the table for the first hour asking for opinions from all. However, maintain discipline once the discussion is started. When a sidebar conversation goes too long, ask those involved to provide an opinion on the question at hand or for a contribution to the main discussion. Sometimes, sidebars produce enlightening ideas.

With a design approach that is methodical and with thoughtful planning in preparation for the PHA or HAZOP, this painful process can effectively serve its purpose.

More from this perspective...

Title

Field Notes: Strive for a Surveyor’s Eye

Surveying and drafting skills can pay off for process people.

09/02/2009

Fight Over-Confidence

Most people aren’t as good as they think at their jobs.

06/21/2012

Finding The True Cost of Data-Collecting Equipment -- Can You Really Afford It?

Consider all costs before you opt to install an instrument.

12/15/2008

Get Pipe Specifications Right in the Beginning!

Good pipe specifications can avoid costly and dangerous mistakes

08/08/2008

Get Your Head Around Shutoff Head

Specifying control valves that may need to provide tight cutoff requires care

08/20/2014

Head Off Hydrogen Hazards

Proper material selection and piping design are crucial

05/05/2014

Heat Exchangers -- Keep Out of Hot Water

Some simple steps can ease heat exchanger commissioning.

02/03/2011

It really isn’t your problem

A manager shouldn’t try to be a Mr. Fix-it.

02/05/2008

Keep Confined Space Work Safe

Rigorous attention to detail is essential to minimize risks and enhance response.

09/27/2010

Keep Current on Your Electrical Measurement Equipment

Electrical measurements often can offer valuable insights.

04/04/2013

Keep plant layout from laying you low

Spot mistakes before they literally become set in stone on the site

05/02/2008

Keeping Peace While Managing Unions

Dealing with unions often poses challenges to engineers

08/07/2008

Know Your Rights

Intellectual property agreements can pose significant concerns.

03/03/2011

Know when to call for help

Sometimes a construction manager is a necessary evil, says Dirk Williard, in this month's Field Notes column.

08/20/2007

Know when to leave a sinking ship

The unspoken truth about projects is that they all come to an end, according to Dirk Willard in this month's Field Notes column. The key, he says, is knowing when to leave.

01/03/2007

Learn Office Politics

Improving your political savvy can help you survive.

01/07/2010

Learning foreign languages can make your job easier

Don’t build walls, by ignoring foreign languages, says Contributing Editor Dirk Willard, in this month's Field Notes column. Learning foreign languages can make your job easier.

10/04/2007

Level transmitter — art not science

There is much more to setting up a transmitter than a mere equation. Design and control errors can certainly compromise performance. Follow these simple tricks to get it right.

06/13/2006

Look at the Big Picture

Ensure that dealing with a safety problem doesn't cause a second risk.

03/22/2012

Maintain an open mind about maintenance options

Sometimes it’s better to take a preventive rather than predictive approach

06/17/2008