Perspectives: Field Notes

Diagram Process Design History: Don't Trip Up on Line Lists

Resolve discrepancies and other problems early.

By Dirk Willard, Contributing Editor

"The test pressure seems too high." It was an honest criticism. We had based our line list on the design pressure of the vessel connected to the drain line and come up with 450 psi, with a testing pressure of 680 psi. However, previous hydrostatic tests of the nearby piping connected to that drain line only had been at 400 psi. Such are the challenges of developing a good line list. So, let's review what to consider when putting together a line list and some of the pitfalls.

The line list should define operating, average and maximum temperature and pressure, design temperature and pressure, pipe specification, special requirements (such as post-weld treatment for caustic and sulfur exposure), and hydrostatic test pressure. Most importantly, it must justify the values selected. A history is useful; to document design history, I make comments in a spreadsheet so they can be viewed later.

The line list should consist of two sections: mechanical and process. The mechanical section often only contains line numbers, connections and tie-points but sometimes includes the pipe specification; if the line list requires mating a 300-psi flange to a 150-psi one, it's mechanical's fault. The process portion covers corrosion, safety and pressure relief.

To develop the line list, you'll need: 1) an approved marked-up piping and instrumentation diagram (I never begin a line list without one!); 2) isometric drawings of normally open connecting pipe; 3) pressure safety valve (PSV) set pressures as well as design pressures for equipment and vessels — these may not agree; 4) field or distributed-control-system readings of average and maximum operating temperature and pressure, preferably over at least two to three years; 5) a process flow diagram (PFD) to define the stream composition and risk should a leak occur; 6) equipment curves, e.g., for pumps; 7) a unit operating manual — this is useful for understanding the unit operation, if the PFD isn't current, which is often the case; and, ideally, 8) a discussion with operations to confirm operating conditions — these frequently get lost in translation between project engineering and operation. If pressure readings are too remote, you may need a hydraulic analysis to estimate the true pressure in a pipe.

List the discrepancies among the collected data. A vessel design pressure may exceed the PSV set pressure. A pipe connected to one on the line list may not match the pressure desirable — usually, the highest pressure is chosen for the design pressure unless it conflicts with normally open connecting pipe. This is an important concept: base line list values on normal conditions, not worst case ones.

Design pressure usually is the vessel design pressure (especially if the pipe connects directly), the deadhead pressure of a pump or compressor, or the PSV set pressure. No hard and fast rules exist. If nothing else is available, refer to the plant standards or add, say, 50 psi to the maximum operating pressure.

Because the design temperature really represents fire conditions where metal softens and withstands less pressure, choose it with care. Normally, opt for the isometric temperatures, not the vessel design temperature. If possible, use the maximum operating temperature plus a safety factor of, say, 50°F. Tracing poses an additional problem. For steam tracing, select the normal saturation temperature of the steam supply. For electric tracing, I have seen 250°F used; constant wattage tracing can have an exposure temperature of 500°F.

Now, let's consider the pressure test. Hydrostatic testing is commonly chosen due to familiarity; some companies set a limit of 100 psig on pneumatic testing for "safety reasons," because of a lack of understanding of dynamics. (See: "Choose the Right Fluid for Your Pressure Test.")

It's good practice to test all utility pipes connected to the process at process pressures. Conduct the test at whichever is higher — the flange rating or the design pressure corrected for temperature — plus a 50% margin. For a design pressure of 300 psig, test pressure = 1.5×Ct×300, where Ct is the temperature correction factor for the pipe material. Here's a useful equation for the design-based test with carbon steel: test pressure = 1.5×(5.293×10-11×T4 – 8.710×10-8×T3 + 4.797×10-5×T2 – 8.656×10-3×T + 1)×design pressure, where T is in °F. The pressure mustn't exceed the flange limit set by the metallurgist — if this is a problem, change the pipe specification and probably the tie-point.

Lastly, most line lists require an inspection specification. For carbon steel, checking 10% of the welds is adequate; X-ray 100% of alloy welds.


dirk.jpgDIRK WILLARD is a Chemical Processing Contributing Editor. You can e-mail him at dwillard@putman.net

More from this perspective...

Title

Safety Statistics Can Get You into a Scrape

Focusing on minor accidents can foster false perceptions.

12/03/2009

Properly Estimate Engineering Hours

Don’t come up short on a project.

11/06/2009

Don’t Gamble With LOTO

Develop a common-sense plan for lockout/tagout.

10/12/2009

Field Notes: Strive for a Surveyor’s Eye

Surveying and drafting skills can pay off for process people.

09/02/2009

Abandon-in-Place Must End

Leaving equipment derelict instead of demolishing it can prove costly.

08/03/2009

Please Don’t Hire Me!

Some contracts simply aren’t worth winning.

07/06/2009

Take the Right Approach to Projects

Remember the real fun begins after approval.

06/12/2009

Don't Dismiss Process Flow Diagrams

Understand the role these diagrams can play and how to use them effectively.

05/14/2009

Don't Let Design Errors Doom Your Project

Engineering quality assurance demands more attention than it usually gets.

04/16/2009

Reduce Your Energy Needs

Achieving savings may provide a powerful career boost.

03/10/2009

Brain Drain Brings Big Headaches

Inexperience and a tough production schedule can be a lethal combination

02/15/2009

Choose Your Next Position Wisely

Finding your dream job takes a bit of soul searching and answering some tough questions.

01/20/2009

Finding The True Cost of Data-Collecting Equipment -- Can You Really Afford It?

Consider all costs before you opt to install an instrument.

12/15/2008

Deftly Deal with Management of Change

Consider some proven tactics to survive this grueling process.

11/20/2008

Make the Most of Contractors

Using hired help effectively starts by treating them as part of your team.

10/15/2008

Correctly Manage Change

How you begin is at least as important as your eventual goal

10/10/2008

Solve the real problem

Sometimes solving a problem causes more harm than good

08/27/2008

Get Pipe Specifications Right in the Beginning!

Good pipe specifications can avoid costly and dangerous mistakes

08/08/2008

Keeping Peace While Managing Unions

Dealing with unions often poses challenges to engineers

08/07/2008

Maintain an open mind about maintenance options

Sometimes it’s better to take a preventive rather than predictive approach

06/17/2008