Perspectives: Field Notes

Finding The True Cost of Data-Collecting Equipment -- Can You Really Afford It?

Consider all costs before you opt to install an instrument.

By Dirk Willard, Contributing Editor

I shudder to think about the cost. The gas chromatograph was the pet project of someone at corporate. It never was meant to be installed in a hot attic with 140 ft of tubing connecting it to a sample port above a fermenter. I went to a week-long class for maintaining it. The instrument provided excellent data on our exhaust fumes — for about three months. The tubing fouled; eventually the detector burned out and I replaced it, but the chromatograph was never used again. All that money spent for a few weeks of data!

During my career, I’ve seen enough bright ideas come and go to make me a little skeptical. Consider what that chromatograph really cost.

First, there were all the hidden labor costs invested in finding the right instrument: preparing a purchase order, reviewing the bids, answering vendor questions, etc.; a trip from St. Louis to Bakersfield, Calif., to decide the layout; and all those meetings. Let’s roughly tally these hours: instrument selection, 80; bid preparation, 40; bidding, 60; bid selection, 40; field trip, 40; basic design, 40; reviewing and amending design(s), 120; bids and hiring local contractor to complete the work or coordinating with maintenance, 60; managing equipment and parts delivery, 40; commissioning, start-up, and hand-over, 80; training, 80; and, of course, miscellaneous, 40. That totals 720 hours. Granted, these hours are generous but they’re not unrealistic.

Although most of these charges are expensed, they still cost something — the time to pursue other opportunities. Several engineers were tied up working on this instrument. The chromatograph required about 18 engineer-weeks, more than one-third of a man-year. As we’ll see, the construction labor pales compared to this.

Now, let’s consider the annual cost. Start with the project cost. Assuming a $12,000 delivery price for the chromatograph plus $9,000 for construction gives a total of $21,000. While the instrument could be stand-alone, it makes sense to connect it to a distributed control system, which adds about $12,000, far more than the construction cost. This brings the project to about $33,000. Of course, the tab would be much more if we factored in the engineering, which was expensed. Let’s use the average reported by the U.S. Department of Labor: $79,000/year (2006); this salary assumes an engineer with mid-level experience. At about 1,880 hr/yr, that’s a billing rate of about $42/hr. This adds about $30,000 to the project cost, so it totals $33,000 + $30,000 = $63,000. Assuming a typical life of about 15 years for the instrument, an interest rate of 10%, a modest salvage value, 40 hr/yr of engineering support, at $1,700, and some maintenance help keeping the tubing clean, at about $1,000/yr, gives an annual cost of about $10,900 — or around $163,500 over 15 years. Even assuming that the instrument lasted this long, the question that should have been considered was: “Are the data it could provide really worth this much per year?”

Perhaps those data were worth the investment. However, many times such spending really doesn’t make sense. How can you avoid mistakes in the future?

My first idea is to limit your losses. Don’t buy instruments for all your plants at once. Vendors sometimes offer tempting discounts for multiple purchases; resist this bargain — use one installation as a pilot program to assess costs, identify improvements and evaluate benefits. Don’t believe any process comparison. A manufacturing scheme sometimes can differ not only between companies but even between plants. A pilot program allows you to come up with a more realistic estimate. If the costs aren’t worth the investment, try another approach; in the case of a chromatograph, look for better laboratory tests.

Next, develop a database on equipment you use everyday: purchase price, replacement cost, downtime, maintenance man hours, engineering man hours and lessons learned. You don’t want to repeat a mistake. A number of programs are available for document control.

Here’s another idea: create a team. Instead of trying to individually duplicate success everywhere in your organization, use the same vendor, the same contractor and the same company engineer(s) to install instruments at various sites. The advantage of this skunk-works approach is that the team will accumulate knowledge with more installation experience. Make sure you capture this knowledge at the end of the project.
At one company I experienced first-hand how well the skunk-works approach can work. The firm assembled an impressive group of engineers and dedicated them to one goal: inventing a reactor that could minimize downtime and revolutionize quality. Each engineer on the team specialized in one or more aspects of the design. Our competition, a giant in the industry, tried and failed many years before. We were successful because management recognized the value of this approach. As with all things, creative, dynamic leadership is an absolute necessity for success.

More from this perspective...

Title

Take a studied approach to plant studies

Carefully address the challenges of managing and directing specialized teams

 

Maintain an open mind about maintenance options

Sometimes it’s better to take a preventive rather than predictive approach

 

A haphazard approach can hobble hazard reviews

Taking some simple steps can help you avoid common pitfalls in assessing changes

 

Keep plant layout from laying you low

Spot mistakes before they literally become set in stone on the site

 

An Alert Operator Is a Safe Operator

Maintaining a good work environment can contribute to a safer plant

 

Field Notes: Strive for a Surveyor’s Eye

Surveying and drafting skills can pay off for process people.

 

Don’t Gamble With LOTO

Develop a common-sense plan for lockout/tagout.

 

Don't Devalue Isometrics

They sometimes can tell you a lot more than P&IDs

 

Don't Zone Out On Area Classifications

Electrical ratings must start with analysis of chemicals present.

 

Don't Push the Envelope

Take a sensible approach to avoid ignition dangers.

 

Silence Kills

Foster an atmosphere where workers speak up about concerns.

 

Do Your Level Best

Level control with dP transmitters appears simple but really isn't.

 

Heat Exchangers -- Keep Out of Hot Water

Some simple steps can ease heat exchanger commissioning.

 

Know Your Rights

Intellectual property agreements can pose significant concerns.

 

Survey the Sources of Electrical Risks

A walk-down helps determine the need for purged electrical boxes.

 

Work On Workarounds

Treat them as problems that can compromise plant safety.

 

Succeed at Process Troubleshooting

Take advantage of five easy techniques to find the root cause of problems.

 

Savor Construction Sites

But make sure the excitement remains enjoyable.

 

Stop Loops Driving You Round the Bend

Practical pointers trump educators' edicts for real-world process control.

 

Weak Oversight Can Doom a Project

Don't timidly accept whatever a contractor proposes.