Perspectives: Field Notes

Finding The True Cost of Data-Collecting Equipment -- Can You Really Afford It?

Consider all costs before you opt to install an instrument.

By Dirk Willard, Contributing Editor

I shudder to think about the cost. The gas chromatograph was the pet project of someone at corporate. It never was meant to be installed in a hot attic with 140 ft of tubing connecting it to a sample port above a fermenter. I went to a week-long class for maintaining it. The instrument provided excellent data on our exhaust fumes — for about three months. The tubing fouled; eventually the detector burned out and I replaced it, but the chromatograph was never used again. All that money spent for a few weeks of data!

During my career, I’ve seen enough bright ideas come and go to make me a little skeptical. Consider what that chromatograph really cost.

First, there were all the hidden labor costs invested in finding the right instrument: preparing a purchase order, reviewing the bids, answering vendor questions, etc.; a trip from St. Louis to Bakersfield, Calif., to decide the layout; and all those meetings. Let’s roughly tally these hours: instrument selection, 80; bid preparation, 40; bidding, 60; bid selection, 40; field trip, 40; basic design, 40; reviewing and amending design(s), 120; bids and hiring local contractor to complete the work or coordinating with maintenance, 60; managing equipment and parts delivery, 40; commissioning, start-up, and hand-over, 80; training, 80; and, of course, miscellaneous, 40. That totals 720 hours. Granted, these hours are generous but they’re not unrealistic.

Although most of these charges are expensed, they still cost something — the time to pursue other opportunities. Several engineers were tied up working on this instrument. The chromatograph required about 18 engineer-weeks, more than one-third of a man-year. As we’ll see, the construction labor pales compared to this.

Now, let’s consider the annual cost. Start with the project cost. Assuming a $12,000 delivery price for the chromatograph plus $9,000 for construction gives a total of $21,000. While the instrument could be stand-alone, it makes sense to connect it to a distributed control system, which adds about $12,000, far more than the construction cost. This brings the project to about $33,000. Of course, the tab would be much more if we factored in the engineering, which was expensed. Let’s use the average reported by the U.S. Department of Labor: $79,000/year (2006); this salary assumes an engineer with mid-level experience. At about 1,880 hr/yr, that’s a billing rate of about $42/hr. This adds about $30,000 to the project cost, so it totals $33,000 + $30,000 = $63,000. Assuming a typical life of about 15 years for the instrument, an interest rate of 10%, a modest salvage value, 40 hr/yr of engineering support, at $1,700, and some maintenance help keeping the tubing clean, at about $1,000/yr, gives an annual cost of about $10,900 — or around $163,500 over 15 years. Even assuming that the instrument lasted this long, the question that should have been considered was: “Are the data it could provide really worth this much per year?”

Perhaps those data were worth the investment. However, many times such spending really doesn’t make sense. How can you avoid mistakes in the future?

My first idea is to limit your losses. Don’t buy instruments for all your plants at once. Vendors sometimes offer tempting discounts for multiple purchases; resist this bargain — use one installation as a pilot program to assess costs, identify improvements and evaluate benefits. Don’t believe any process comparison. A manufacturing scheme sometimes can differ not only between companies but even between plants. A pilot program allows you to come up with a more realistic estimate. If the costs aren’t worth the investment, try another approach; in the case of a chromatograph, look for better laboratory tests.

Next, develop a database on equipment you use everyday: purchase price, replacement cost, downtime, maintenance man hours, engineering man hours and lessons learned. You don’t want to repeat a mistake. A number of programs are available for document control.

Here’s another idea: create a team. Instead of trying to individually duplicate success everywhere in your organization, use the same vendor, the same contractor and the same company engineer(s) to install instruments at various sites. The advantage of this skunk-works approach is that the team will accumulate knowledge with more installation experience. Make sure you capture this knowledge at the end of the project.
At one company I experienced first-hand how well the skunk-works approach can work. The firm assembled an impressive group of engineers and dedicated them to one goal: inventing a reactor that could minimize downtime and revolutionize quality. Each engineer on the team specialized in one or more aspects of the design. Our competition, a giant in the industry, tried and failed many years before. We were successful because management recognized the value of this approach. As with all things, creative, dynamic leadership is an absolute necessity for success.

More from this perspective...

Title

Finding The True Cost of Data-Collecting Equipment -- Can You Really Afford It?

Consider all costs before you opt to install an instrument.

 

Choose Your Next Position Wisely

Finding your dream job takes a bit of soul searching and answering some tough questions.

 

Deftly Deal with Management of Change

Consider some proven tactics to survive this grueling process.

 

Make the Most of Contractors

Using hired help effectively starts by treating them as part of your team.

 

Correctly Manage Change

How you begin is at least as important as your eventual goal

 

Brain Drain Brings Big Headaches

Inexperience and a tough production schedule can be a lethal combination

 

Reduce Your Energy Needs

Achieving savings may provide a powerful career boost.

 

Please Don’t Hire Me!

Some contracts simply aren’t worth winning.

 

Abandon-in-Place Must End

Leaving equipment derelict instead of demolishing it can prove costly.

 

Take the Right Approach to Projects

Remember the real fun begins after approval.

 

Don't Dismiss Process Flow Diagrams

Understand the role these diagrams can play and how to use them effectively.

 

Don't Let Design Errors Doom Your Project

Engineering quality assurance demands more attention than it usually gets.

 

Get Pipe Specifications Right in the Beginning!

Good pipe specifications can avoid costly and dangerous mistakes

 

Keeping Peace While Managing Unions

Dealing with unions often poses challenges to engineers

 

Build reliability in during design

Instrumentation that promises to improve reliability may not always be what they seem. You have to consider whether a site can properly maintain sophisticated instruments.

 

It really isn’t your problem

A manager shouldn’t try to be a Mr. Fix-it.

 

Make the most of newly hired, experienced engineers

Contributing Editor Dirk Willard reminds readers that an old dogs can learn new tricks and plants should keep this in mind when hiring new, yet experienced, engineers.

 

Learning foreign languages can make your job easier

Don’t build walls, by ignoring foreign languages, says Contributing Editor Dirk Willard, in this month's Field Notes column. Learning foreign languages can make your job easier.

 

Don’t get zapped by spark testing

Understand the intricacies of checking for defects in a liner, advises Dirk Willard, contributing editor, in this month's Field Notes column.

 

Stick to the basics

Getting immersed in details can doom a basic design contract to financial failure.