Q: We want to install one new close loop for temperature control. Before tuning the control valve, what should be the initial P, I, D value?
A:
The correct settings depend upon the dynamics of the process and the objective of the loop but here are some initial guesses for some major types of temperature control applications. I have set the reset time based on typical sizes of the volume (lowest for heat exchanger and highest for column), and set the controller gain based on the time constant to dead time ratio (lowest for heat exchanger and highest for vessel). The rate time is set at 1/10 of the reset time. The first number for a setting is a default if you know nothing about the loop. The numbers in parentheses are typical minimum and maximum values (typical range of settings). If you are outside of the range shown, you have an unusual loop.
It is difficult to generalize but I have found these settings to be better than the ones typically set in the configuration by system integrators who are not privy to the process details and dynamics. All loops should be closely monitored when commissioned and tuned with an auto tuner or adaptive tuner.
Application Gain Reset Time (sec/repeat) Rate Time (sec)
Heat Exchanger 0.5 (0.2-2.0) 60 (30-300) 6 (3-30)
Vessel 5.0 (2.0-20) 600 (300-3000) 60 (30-300)
Column 2.0 (1.0-10) 1200 (600-6000) 120 (60-600)
Here are more of the latest questions on: Instrumentation and Control
Can you explain a split range controller?
Regarding split range controller:
- Is it normal to have a control valve with two different sizes?
- Why use a split range controller and where can we it?
- My application: I am planning to use at outlet of condenser. The outlet will have condensate liquid and non-condensate vapor. Will it work here?
Can you explain linearity and accuracy of flowmeters?
I am confused on linearity and accuracy of flowmeters such as oval meters. In some references they are mentioned as the same but in some others they are not the same. Should I only rely on linearity for selection for measuring custody transfer or another flowmeter characteristic?
Can you recommend a flowmeter?
We are going to install a flowmeter for lube oil loading as custody transfer. The flowrate may alter between 140-280 CMH (two-speed motor) having viscosity 150cSt at 40C. Simple installation and setting up on the line and reasonable cost as well as pressure drop are preferred. The pump can generate 8barg pressure. What would be the recommended flow measuring type to support the requested service?
Where should I install the control valve on the hot oil line?
I am going to use hot oil for heating a process in a jacketed vessel and I am going to make a control loop for controlling the vessel content. The hot oil enters at the bottom of the jacket and exits from the top. The control elements are RTD, controller, and control valve. My question: Where should I install the control valve on the hot oil line? Is it up stream or down stream of the vessel?
Why is there a discrepancy of solids at sampling points?
Ours is a fertilizer industry and within the premises we transfer phosphoric acid from the phosphoric acid production facility to the fertilizer production facility. The distance of the pipeline might be around 400m but the difference in issue and receipts generally comes out to be 100s of tons per day. Can you tell me what could be the possible problem? Other info required:
- Phosphoric acid has around 5% solids
- Sampling point in phosphoric acid tank is at the bottom
- Sampling point in the fertilizer plant is at a higher level(25 ft) and is preceded by a lot of bends.